124094 |
Consultancy Services for Feasibility Study cum DPR, Survey and Preparation of Land Plan by adopting LiDAR or similar technology for Widening to two lane with Paved Shoulders Indi-Zalki-Chadachan-Shiradon – Maharahstra Border . |
Under Implementation |
Awarded, not Appointed |
RO MoRTH Bengaluru |
NH Division, Bijapur |
RO MoRTH Bengaluru |
20-Feb-20 |
20-Feb-20 |
MoRTH |
124092 |
Consultancy Services for Feasibility Study cum DPR, Survey and Preparation of Land Plan by adopting LiDAR or similar technology for Widening to two lane with Paved Shoulders Junction of NH-50 near Hungund-Aihole-Pattadakal-Badami-Ramdurg for an approximate length 85.00 km in the State of Karnataka.-857 |
Under Implementation |
Awarded, not Appointed |
RO MoRTH Bengaluru |
NH Division, Bijapur |
RO MoRTH Bengaluru |
20-Feb-20 |
20-Feb-20 |
MoRTH |
124089 |
Vijayapura-Yatnal Guddapur-Jath-Junction of NH-166 Near Nagaj (Vijayapura-Yatnal) about 30.00 kms & Providing by pass to Vijayapura City from NH-13 (Old) Solapur-Vijayapura Section Connecting this road about 17.00 Kms for length 47.00 km |
Under Implementation |
Awarded, not Appointed |
RO MoRTH Bengaluru |
NH Division, Bijapur |
RO MoRTH Bengaluru |
20-Feb-20 |
20-Feb-20 |
MoRTH |
50486 |
Chitradurga-Shimoga |
Under Implementation |
Under Const. |
RO MoRTH Bengaluru |
NH Division, PPP Cell, Shimoga |
RO MoRTH Bengaluru |
20-Feb-20 |
20-Feb-20 |
MoRTH |
50484 |
Madhugiri-Chikkaballapura- Mulbagal Section Km 343.800 to Km 400.330 Lot -I of NH-234 |
Under Implementation |
Under Const. |
RO MoRTH Bengaluru |
NH Division, PPP Cell, Chikkballapura |
RO MoRTH Bengaluru |
20-Feb-20 |
20-Feb-20 |
MoRTH |
50485 |
Rehabiliatation and Upgrading to 2 lanes/ 2 lanes with paved shoulders from Km.400.330 to Km.483.151 -Lot-II of NH-234 |
Under Implementation |
Under Const. |
RO MoRTH Bengaluru |
NH Division, PPP Cell, Chikkballapura |
RO MoRTH Bengaluru |
20-Feb-20 |
20-Feb-20 |
MoRTH |
50437 |
Bijapur-Hubli section Km 153.00 to Km 193.350 |
Under Implementation |
Under Const. |
RO MoRTH Bengaluru |
NH Division, Hubli |
RO MoRTH Bengaluru |
20-Feb-20 |
20-Feb-20 |
MoRTH |
146190 |
Widening of CC pavement in km 0/035 - 1/230 including widening and strengthening of existing bituminous surface in km 0/0 - 0/035, reconstruction of storm water drain at km 0/0-1/400 & construction of crash barrier type center median and paved shoulders of NH45A in the state of Tamil Nadu |
Under Implementation |
Under Const. |
RO MoRTH Chennai |
NHDivisionVillupuram |
PD-NH Division Villupuram |
16-Feb-20 |
26-Dec-19 |
MoRTH |
137819 |
Widening of Four Lane, Construction of Storm water drain, centre median and providing paver block from Km 2/4-7/4 of NH45A (Villupuram - Pondy - Nagapattinam Road) |
Under Implementation |
Under Const. |
RO MoRTH Chennai |
NHDivisionVillupuram |
PD-NH Division Villupuram |
16-Feb-20 |
26-Dec-19 |
MoRTH |
146192 |
Widening of CC Pavement to km.1/800- 2/400 including widening and strengthening of existing bituminous surface from km.1/230-1/400 & 1/760-1/800, strengthening in km.1/400-1/760, Reconstruction of storm water drain at Km 1/800-2/400, constrution of crash barrier type center median and paved shoulders of NH45A (Villupuram-Pondicherry-Nagapattinam road) in the state of Tamil Nadu |
Under Implementation |
Under Const. |
RO MoRTH Chennai |
NHDivisionVillupuram |
PD-NH Division Villupuram |
16-Feb-20 |
26-Dec-19 |
MoRTH |
55560 |
Strengthening with paved shoulder from km 858/000 to 862/000, 868/000 to 875/000, 876/000 to 879/000, from Km 888/0 to 892/0, Km 907/0 to 912/348 and Km 912/780 to 915/0 including paved shoulder from Km 862/000 to 868/000 and 875/000 to 876/000 |
Under Implementation |
Under Const. |
RO MoRTH Guwahati |
Construction Division Abhayapuri |
Construction Division Abhayapuri |
10-Feb-20 |
28-Nov-19 |
MoRTH |
143623 |
Widening and improvement of Kajri Patan Manatu Road from km 16.40 to 34.40 |
Under Implementation |
Under Const. |
RO MoRTH Ranchi |
Road Division, Daltonganj |
RO MoRTH Ranchi |
10-Feb-20 |
10-Feb-20 |
MoRTH |
143486 |
Construction of Box cell culverts at km 140/200 km, 147/400 km & 155/100 km of NH - 23 |
Under Implementation |
Under Const. |
RO MoRTH Ranchi |
NH Division Gumla |
RO MoRTH Ranchi |
10-Feb-20 |
10-Feb-20 |
MoRTH |
143319 |
Strengthening of road from km 0.00 to km 41.80 of NH - 133A |
Under Implementation |
Under Const. |
RO MoRTH Ranchi |
NH Division Deoghar |
RO MoRTH Ranchi |
10-Feb-20 |
10-Feb-20 |
MoRTH |
143305 |
Strengthening of road from km 73.00 to 119.175 of NH - 100 |
Under Implementation |
Under Const. |
RO MoRTH Ranchi |
NH Division Hazaribagh |
RO MoRTH Ranchi |
10-Feb-20 |
10-Feb-20 |
MoRTH |
143310 |
Construction of Box cell culverts in km 49.00 to 62.00 of NH - 100 |
Under Implementation |
Under Const. |
RO MoRTH Ranchi |
NH Division Hazaribagh |
RO MoRTH Ranchi |
10-Feb-20 |
10-Feb-20 |
MoRTH |
143267 |
Strengthening of road from km. 44.00 to km. 71.00 of NH - 143A |
Under Implementation |
Under Const. |
RO MoRTH Ranchi |
NH Division Gumla |
RO MoRTH Ranchi |
10-Feb-20 |
10-Feb-20 |
MoRTH |
143271 |
Strengthening of road from km. 10.00 to km. 23.215 of NH-78 |
Under Implementation |
Under Const. |
RO MoRTH Ranchi |
NH Division Gumla |
RO MoRTH Ranchi |
10-Feb-20 |
10-Feb-20 |
MoRTH |
143302 |
Strengthening work of Hatgamharia-Jaintgarah road from km. 176.000 to 202.900 of NH - 75Ext. |
Under Implementation |
Under Const. |
RO MoRTH Ranchi |
NH Division Chaibaja |
RO MoRTH Ranchi |
10-Feb-20 |
10-Feb-20 |
MoRTH |
123421 |
Construction of new bridge over Durangi Nala in 108th km of NH-75 |
Under Implementation |
Under Const. |
RO MoRTH Ranchi |
NH Division Ranchi |
RO MoRTH Ranchi |
10-Feb-20 |
10-Feb-20 |
MoRTH |
122536 |
Strengthening work in Km 12.325 to 62.760 of NH-114A |
Under Implementation |
Under Const. |
RO MoRTH Ranchi |
NH Division Deoghar |
RO MoRTH Ranchi |
10-Feb-20 |
10-Feb-20 |
MoRTH |
122535 |
Strengthening work in Km 29.50 to 48.05 & Km 52.03 to 57.00 of NH-98 |
Under Implementation |
Under Const. |
RO MoRTH Ranchi |
NH Division Medininagar |
RO MoRTH Ranchi |
10-Feb-20 |
10-Feb-20 |
MoRTH |
68314 |
Widening to 2-lane with paved shoulder & improvement from Km 41.00 to 54.00 of NH-220 in the state of Jharkhand. |
Under Implementation |
Under Const. |
RO MoRTH Ranchi |
NH Division Chaibaja |
RO MoRTH Ranchi |
10-Feb-20 |
10-Feb-20 |
MoRTH |
64844 |
Widening to two lane with paved shoulder & Geometric Improvements from Km 184 to 216 on NH-114A |
Under Implementation |
Under Const. |
RO MoRTH Ranchi |
NH Division Dhanbad |
RO MoRTH Ranchi |
10-Feb-20 |
10-Feb-20 |
MoRTH |
59042 |
Widening and Strengthening work in Km 141 to 184 of NH-114A |
Under Implementation |
Under Const. |
RO MoRTH Ranchi |
NH Division Deoghar |
RO MoRTH Ranchi |
10-Feb-20 |
10-Feb-20 |
MoRTH |
58749 |
Construction of HL bridge over Local Nala in km 118 of NH-343 |
Under Implementation |
Under Const. |
RO MoRTH Ranchi |
NH Division Medininagar |
RO MoRTH Ranchi |
10-Feb-20 |
10-Feb-20 |
MoRTH |
58748 |
Construction of HL bridge over Local Nala in km 113 of NH-343 |
Under Implementation |
Under Const. |
RO MoRTH Ranchi |
NH Division Medininagar |
RO MoRTH Ranchi |
10-Feb-20 |
10-Feb-20 |
MoRTH |
50837 |
Widening and Strengthening work in Km 0 to 12.80 of NH-333A |
Under Implementation |
PCOD |
RO MoRTH Ranchi |
NH Division Deoghar |
RO MoRTH Ranchi |
10-Feb-20 |
10-Feb-20 |
MoRTH |
50831 |
bridge in km 102.60, 107.185, 107.368 & 115.875 of NH-99 |
Under Implementation |
Under Const. |
RO MoRTH Ranchi |
NH Division Ranchi |
RO MoRTH Ranchi |
10-Feb-20 |
10-Feb-20 |
MoRTH |
50815 |
Remaining work of Widening to intermediate lane and improvement of Sisai Basia Road from Km 0.0 to 37.775 |
Under Implementation |
Under Const. |
RO MoRTH Ranchi |
Road Division Gumla |
RO MoRTH Ranchi |
10-Feb-20 |
10-Feb-20 |
MoRTH |
50817 |
Widening and Strengthening of 2 Lane & Improvement of Lohardaga Kisko More to Richuguta Road from Km 0.00 to 31.50 (balance work) |
Under Implementation |
Under Const. |
RO MoRTH Ranchi |
Road Division, Lohardaga |
RO MoRTH Ranchi |
10-Feb-20 |
10-Feb-20 |
MoRTH |
50812 |
bridge in km 95.37, 98.19 and 100.87 of NH-75 |
Under Implementation |
Under Const. |
RO MoRTH Ranchi |
NH Division Ranchi |
RO MoRTH Ranchi |
10-Feb-20 |
10-Feb-20 |
MoRTH |
50801 |
Widening and Strengthening of Road work and reconstruction of culverts in km 31 to 61 (Chainage km 30 to 60.50) of NH-99 |
Under Implementation |
Under Const. |
RO MoRTH Ranchi |
NH Division Hazaribagh |
RO MoRTH Ranchi |
10-Feb-20 |
10-Feb-20 |
MoRTH |
50797 |
Construction of bridge in km 75/1, 76/1, 78/4 & 78/8 of NH-99 (Part-4) |
Under Implementation |
Under Const. |
RO MoRTH Ranchi |
NH Division Hazaribagh |
RO MoRTH Ranchi |
10-Feb-20 |
10-Feb-20 |
MoRTH |
50793 |
bridge over Katabil Nala |
Under Implementation |
Under Const. |
RO MoRTH Ranchi |
NH Division Ranchi |
RO MoRTH Ranchi |
10-Feb-20 |
10-Feb-20 |
MoRTH |
50796 |
Construction of bridge in km 37/1, 39/1 of NH-99 (Part-2) |
Under Implementation |
Under Const. |
RO MoRTH Ranchi |
NH Division Hazaribagh |
RO MoRTH Ranchi |
10-Feb-20 |
10-Feb-20 |
MoRTH |
50784 |
Construction of bridges in km 250.300, 252 & 256 of NH-75 |
Under Implementation |
Under Const. |
RO MoRTH Ranchi |
NH Division Medininagar |
RO MoRTH Ranchi |
10-Feb-20 |
10-Feb-20 |
MoRTH |
102069 |
Construction of Signature Bridge between Dwarka & bey Dwarka and its approaches in the State of Gujarat on EPC Mode [NH-51/Gujarat(02) 17-20-S & R (B)] |
Under Implementation |
Under Const. |
RO MoRTH Gandhinagar |
NH Division Rajkot |
NH Division Rajkot |
10-Feb-20 |
25-Oct-19 |
MoRTH |
148718 |
Construction of 6.00 Mtr Span Double lane Class A loading RCC Culvert in km 175 (HM-2-4) of NH-309A in the state of Uttarakhand under NH(O) Annual plan 2018-19 |
Under Implementation |
Awarded, not Appointed |
RO MoRTH Dehradun |
NH Division Ranikhet |
NH Division Ranikhet |
10-Feb-20 |
12-Oct-19 |
MoRTH |
144101 |
"I.R.Q.P Work from km 23.20 to km 25.70 of N.H.-34 under N.H Division No.V, P.W.(Roads) Directorate in the District of North 24 Parganas, West Bengal during the 2018-19 on SBD mode. (Job No.034-WB-2016-17/431)" |
Under Implementation |
Under Const. |
RO MoRTH Kolkata |
NH Division-V |
NH Division-V |
6-Feb-20 |
17-Oct-19 |
MoRTH |
58469 |
Construction of Twins 2-lane ROB and its approaches in replacement of existing level crossing Gate No. -KA-34 (Rly km 160/25-160/27) between Mindapore & Bankura stations in Kubai at km 154.617 of NH-60. |
Under Implementation |
Under Const. |
RO MoRTH Kolkata |
NH Division-II |
NH Division-II |
5-Feb-20 |
17-Oct-19 |
MoRTH |
62565 |
Reconstruction With geometric improvement of existing two lane to 2- Lane with paved shoulders configuration from existing Km. 126.73 to 135.075 & km.143.75 to 163.00(Pithoragarh-Tanakpur Project road)of NH-125 in the state of UttaraKhand on EPC mode |
Under Implementation |
Under Const. |
RO MoRTH Dehradun |
NH Division Lohaghat |
NH Division Lohaghat |
4-Feb-20 |
12-Oct-19 |
MoRTH |
62567 |
Reconstruction with geometric improvement of single/intermediate Lane to 2- Lane with paved shoulder configuration from existing Km. 92.880 to Km 121.550 (Design chainage 91.550 to120.455) of NH-125 in the state of UttaraKhand on EPC mode |
Under Implementation |
Under Const. |
RO MoRTH Dehradun |
NH Division Lohaghat |
NH Division Lohaghat |
4-Feb-20 |
12-Oct-19 |
MoRTH |
60147 |
Reconstruction of existing 2 L/IL to 2L with paved shoulder from existing km 52.200 to 92.880 of NH- |
Under Implementation |
Under Const. |
RO MoRTH Dehradun |
NH Division Lohaghat |
NH Division Lohaghat |
4-Feb-20 |
12-Oct-19 |
MoRTH |
62566 |
Reconstruction With geometric improvement of single Lane to 2- Lane with paved shoulder configuration from existing Km. 163.00 to Km 194.800(Design chainage 160.88 to 192.320) of NH-125 in the state of UttaraKhand on EPC mode |
Under Implementation |
Under Const. |
RO MoRTH Dehradun |
NH Division Lohaghat |
NH Division Lohaghat |
4-Feb-20 |
12-Oct-19 |
MoRTH |
149422 |
Stage Strengthening of the existing pavement from 0.00 Kmp to 49.00 kmp of NH- 2B under National Highway Division No:-III of N.H.C.-II during the year 2019-20 in the district of Purba Bardhaman & Birbhum ,West Bengal in EPC Mode. (Job No. 26-WB-2019-20/441) |
Under Implementation |
Awarded, not Appointed |
RO MoRTH Kolkata |
NH Division-III |
NH Division-III |
3-Feb-20 |
|
MoRTH |
149421 |
Stage Strengthening from 260 kmp to 266 kmp and 271 kmp to 275 kmp (except 273.05 km to 273.85 km) of NH-60 under N.H Division No.III, P.W.(Roads) Directorate in the District of Bankura & Paschim Bardhaman, West Bengal on EPC mode. (Job No. 60-WB-2019-20/440) |
Under Implementation |
Under Const. |
RO MoRTH Kolkata |
NH Division-III |
NH Division-III |
3-Feb-20 |
|
MoRTH |
122754 |
Tolakurwa to Bishnupur ( via Chakai) |
Under Implementation |
Under Const. |
RO MoRTH Patna |
NH Division Lakhisarai |
NH Division Lakhisarai |
3-Feb-20 |
11-Dec-19 |
MoRTH |
62910 |
HL RCC minor bridge in km 24 |
Under Implementation |
Under Const. |
RO MoRTH Patna |
NH Division Lakhisarai |
NH Division Lakhisarai |
3-Feb-20 |
11-Dec-19 |
MoRTH |
124078 |
Construction ofProposed 4-Lane ROBand its approaches in lieu of existing level crossing No. 95/SPL @ Km 272.600( Railway Chainage 93/17-19) on NH 205 in the State of A.P. Job No. NH-205 /AP(36)/17-S&R(B)018 dt 07-07-2017 |
Under Implementation |
Under Const. |
RO MoRTH Vijayawada |
NH Division KADAPA |
NH Division KADAPA |
3-Feb-20 |
13-Dec-19 |
MoRTH |
54163 |
Widening and strengthening of existing single /2lane to 2 lane with earthen shoulder configuration from km. 57.975 to km. 68.600 (Fata to Sitapur) on NH-109(New No. 107) in the State of Uttarakhand under EPC Mode |
Under Implementation |
Under Const. |
RO MoRTH Dehradun |
NH Division Rudraprayag |
NH Division Rudraprayag |
7-Jan-20 |
12-Oct-19 |
MoRTH |
50274 |
Construction of 2-lane with paved shoulders configuration & strengthening of NH-58 from km 350.00 to km. 355.00 (Kaliyasaur re-alignment) in the State of Uttarakhand on EPC Mode |
Under Implementation |
Under Const. |
RO MoRTH Dehradun |
NH Division Rudraprayag |
NH Division Rudraprayag |
6-Jan-20 |
12-Oct-19 |
MoRTH |
55566 |
Strengthening with paved shoulders from Km 138/00 to 157/0 and Km 171/0 to 177/0 (Total length= 25.00 km.) under Nagaon NH Division (Job No. 052(New-15)/AS/2016-17/164 |
Under Implementation |
Under Const. |
RO MoRTH Guwahati |
NH Division Nagaon |
NH Division Nagaon |
6-Jan-20 |
28-Nov-19 |
MoRTH |
62130 |
Construction & Widening (Including Augustmuni Bypass Ch-16.545 to Ch - 19.890) to 2L/PS from Km 16.545-Km 33.130 & 45.980 -57.975 (Augustmuni to Kund & Guptkashi to Sitapur) on NH 109 in UK |
Under Implementation |
Under Const. |
RO MoRTH Dehradun |
NH Division Rudraprayag |
NH Division Rudraprayag |
6-Jan-20 |
12-Oct-19 |
MoRTH |
50701 |
Strengthening with paved shoulder from KM. 305/0 to 316/0 of NH-52(Total length=11.00 Km.) including providing retaining walls breast walls, culverts and drains in selected stretches under Nagaon NH Division in the state of Assam on E.P.C mode (Job No.052/AS/2014-15/124) |
Under Implementation |
Under Const. |
RO MoRTH Guwahati |
NH Division Nagaon |
NH Division Nagaon |
6-Jan-20 |
28-Nov-19 |
MoRTH |
124192 |
Strengthening with construction of paved shoulders from km 135/000 to km 138/000, km157/000 to 171/000 and km 177/000 to km 182/000 (Total Length = 22.00 km) of NH-52 (New NH-15) FOR THE YEAR 2017-18 UNDER Nagaon NH Division in the State of Assam. (Job No. 052(New NH-15)/AS/2017-18/180) |
Under Implementation |
Under Const. |
RO MoRTH Guwahati |
NH Division Nagaon |
NH Division Nagaon |
6-Jan-20 |
28-Nov-19 |
MoRTH |
143514 |
Construction of 2 lane NH with paved shoulders between Ch.396.4215 km and Ch.397.9885 km of NH-52(New NH-15) ,bituminous layers between Ch.407.428 km and Ch.408.030 km,Ch.419.99km and Ch. 440.000km of NH-52(New NH-15)for 10.00m width and between Ch. 436.760 km and Ch .436.915 km for 5.00 m width of NH-52 (New NH-15) and rehabilitation of bridge No. 308/1 opver river Kumatia including construction of guide bunds,river training work etc in Assam . SARDP-NE NH-15/AS/PWD/2016-17/289 |
Under Implementation |
Under Const. |
RO MoRTH Guwahati |
NH Division Nagaon |
NH Division Nagaon |
4-Jan-20 |
28-Nov-19 |
MoRTH |
68031 |
Rehabilitation and upgradation of Dornala T junction to Penchalakona Km 361/327 to 425/4 of Nh-565 in the state of Andhra Pradesh. |
Under Implementation |
Under Const. |
RO MoRTH Vijayawada |
NH Division KADAPA |
NH Division KADAPA |
3-Jan-20 |
13-Dec-19 |
MoRTH |
60530 |
Rehabilitation and up-gradation of NH-340 from km 0+000 to km 60+380 (Design Ch. 0/000 to 60/025) (Rayachoty to Angallu section) to two lane with paved shoulders in the State of Andhra Pradesh under Corridor Approach through Engineering, Procurement & Con |
Under Implementation |
Under Const. |
RO MoRTH Vijayawada |
NH Division KADAPA |
NH Division KADAPA |
3-Jan-20 |
13-Dec-19 |
MoRTH |
137317 |
Construction of 4-Lane ROBand its approaches in lien of existing level crossing No. 102/3E @ Km 281.200 of NH 205 in the State of A.P. Job No. NH-205 /AP(8)/15-16-010-S&R(B) dt 31-03-2016 |
Under Implementation |
Under Const. |
RO MoRTH Vijayawada |
NH Division KADAPA |
NH Division KADAPA |
3-Jan-20 |
13-Dec-19 |
MoRTH |
144084 |
Construction of ROB in km 24 (LC no. 77A) of NH 327A |
Under Implementation |
Awarded, not Appointed |
RO MoRTH Patna |
NH Division Madhepura |
NH Division Madhepura |
3-Jan-20 |
11-Dec-19 |
MoRTH |
144081 |
Construction of ROB in km 194 (LC no. 53B/T-2) of NH 327E |
Under Implementation |
Awarded, not Appointed |
RO MoRTH Patna |
NH Division Madhepura |
NH Division Madhepura |
3-Jan-20 |
11-Dec-19 |
MoRTH |
52320 |
Widening and Strengthening of existing carriageway for 4-laning of NH-34 for the stretch from Km. 25.700 to Km. 31.00 |
Under Implementation |
Under Const. |
RO MoRTH Kolkata |
NH Division-V |
NH Division-V |
2-Jan-20 |
17-Oct-19 |
MoRTH |
80176 |
Reconstruction of Bridge across river Pravadayanar @Ch 184/000 in NH45A in Karaikal district in the Unioun territory of Pondicherry |
Under Implementation |
Under Const. |
RO MoRTH Chennai |
PWD, Karaikal |
RO MoRTH Chennai |
26-Dec-19 |
26-Dec-19 |
MoRTH |
54027 |
Villupuram-Puducherry |
Under Implementation |
Under Const. |
RO MoRTH Chennai |
PWD, Puducherry |
RO MoRTH Chennai |
26-Dec-19 |
26-Dec-19 |
MoRTH |
148635 |
Construction of 4 Lane ROB and Subway in lien of level crossing no. 17 @ km 108/1-2 between Jamalamagudu & Proddator Station on Nandyal-Yerraguntla section at km 563/200 of NH-67 EPC mode in the state of A.P. Job No. NH-67-AP-17-18-672 dt 28-03-2018 |
Under Implementation |
Under Const. |
RO MoRTH Vijayawada |
NH Division KADAPA |
RO MoRTH Vijayawada |
13-Dec-19 |
13-Dec-19 |
MoRTH |
144969 |
Rehabilitiation and upgradation of Chittoor - Kurnool Road NH-18 (New NH-40) from 2 lane to 4 Lane from Km 4/14 to 18/34 (excluding 2.94 Km ROB Portion) from Murkumbattu Junction to Rangampet cross in the State of Andhra Pradesh through EPC mode |
Under Implementation |
Under Const. |
RO MoRTH Vijayawada |
NH Division Chittor |
RO MoRTH Vijayawada |
13-Dec-19 |
13-Dec-19 |
MoRTH |
144967 |
Improvement to NH-544D(Anantapur-Guntur Road) from Km 414 to 417 (i.d.) from Chuttugunta junction to NH-16 junction) including widening in Guntur Municipal limits in the state of Andhra Pradesh on EPC mode. |
Under Implementation |
Under Const. |
RO MoRTH Vijayawada |
NH Division VIJAYAWADA |
RO MoRTH Vijayawada |
13-Dec-19 |
13-Dec-19 |
MoRTH |
141388 |
Construction of proposed 4- lane RoB at Railway Chainage km 44/679 between Puthalapattu -RVS Nagar Station of kathipudi- pakala Section @km 12/4 on NH 18 in the state of Andhra Pradesh on EPC Mode [job.no. 18-AP-2018-19-676 dt:16.01.19 |
Under Implementation |
Under Const. |
RO MoRTH Vijayawada |
NH Division Chittor |
RO MoRTH Vijayawada |
13-Dec-19 |
13-Dec-19 |
MoRTH |
141387 |
Strenghtening in selected stretches (25.6) from km 0/0 to 4/0, km 16/0 to 22/2, km 23/2 to 24/4, km 30/4 to 32/2, km 33/0 to 39/0, km 53/0 to 54/6, km 55/9 to 56/5, km 58/0 to 59/1 , km 60/0 to 60/6 & km 61/4 to 63/9 of Renigunta to kadapa Road NH-716 in the state of A.P. [Job.no. 716-AP-2018-19-675 dt: 09.01.19 |
Under Implementation |
Under Const. |
RO MoRTH Vijayawada |
NH Division KADAPA |
RO MoRTH Vijayawada |
13-Dec-19 |
13-Dec-19 |
MoRTH |
141386 |
Improvement the selected stretches (21.20 km) to the road from km. 0/0 to 40/2 of puttur-Uthukottai road NH-716A in the state of Andhra Pradesh on EPC mode [job.no. 716A-AP-2018-19-674 dt:04.12.18] |
Under Implementation |
Under Const. |
RO MoRTH Vijayawada |
NH Division KADAPA |
RO MoRTH Vijayawada |
13-Dec-19 |
13-Dec-19 |
MoRTH |
139241 |
Construction of Proposed 4-Lane ROB and its approaches in lien of existing level crossing No. 67 @ Km 133.20( Railway Chainage 109/3-4) on NH 205 in the State of A.P. Job No. NH-205 /AP(38)/16-17-013-S&R(B) dt 24-03-2017 |
Under Implementation |
Under Const. |
RO MoRTH Vijayawada |
NH Division Chittor |
RO MoRTH Vijayawada |
13-Dec-19 |
13-Dec-19 |
MoRTH |
139239 |
Construction of Proposed 4-Lane ROB and its approaches in lien of existing level crossing No. 75 @ Km 145.200( Railway Chainage 121/470) on NH 205 in the State of A.P. Job No. NH-205 /AP(4)/17-S&R(B)020 dt 07-07-2017 |
Under Implementation |
Under Const. |
RO MoRTH Vijayawada |
NH Division Chittor |
RO MoRTH Vijayawada |
13-Dec-19 |
13-Dec-19 |
MoRTH |
139238 |
Construction ofProposed 4-Lane ROBand its approaches in lien of existing level crossing No. 45 C @ Km 93.40( Railway Chainage 70/903) on NH 205 in the State of A.P. Job No. NH-205 /AP(3)/17-S&R(B)019 dt 07-07-2017 |
Under Implementation |
Under Const. |
RO MoRTH Vijayawada |
NH Division ANANTAPUR |
RO MoRTH Vijayawada |
13-Dec-19 |
13-Dec-19 |
MoRTH |
139237 |
Construction ofProposed 4-Lane ROBand its approaches in lien of existing level crossing No. 48E/C @ Km 96.80( Railway Chainage 74.431) on NH 205 in the State of A.P. Job No. NH-205 /AP(39)/16-17-012-S&R(B) dt 22-03-2017 |
Under Implementation |
Under Const. |
RO MoRTH Vijayawada |
NH Division ANANTAPUR |
RO MoRTH Vijayawada |
13-Dec-19 |
13-Dec-19 |
MoRTH |
137320 |
Construction ofProposed 4-Lane ROBand its approaches in lien of existing level crossing No. 30/E @ Km 64.800( Railway Chainage 42.858) on NH 205 in the State of A.P. Job No. NH-205 /AP(1)/16-17-016-S&R(B) dt 31-03-2017 |
Under Implementation |
Under Const. |
RO MoRTH Vijayawada |
NH Division ANANTAPUR |
RO MoRTH Vijayawada |
13-Dec-19 |
13-Dec-19 |
MoRTH |
137315 |
Construction of 4-Lane ROB and its approaches in lien of existing level crossing No.124E/SPL 3@ Km 1.800( New Chainage km 77.805 on NH 205 in the State of A.P. Job No. NH-205 /AP(2)/15-16-007-S&R(B) dt 14-03-2016 |
Under Implementation |
Under Const. |
RO MoRTH Vijayawada |
NH Division ANANTAPUR |
RO MoRTH Vijayawada |
13-Dec-19 |
13-Dec-19 |
MoRTH |
124086 |
Construction of 2-Lane ROB and its approaches in lien of level crossing No.414 @ Km 33.100 (Railway chainage 730/11-13) on NH-326A on EPC mode in the State of A.P. Job No. NH-326A-AP17-18 -671 dt 28-03-2018. |
Under Implementation |
Under Const. |
RO MoRTH Vijayawada |
NH Division KAKINADA |
RO MoRTH Vijayawada |
13-Dec-19 |
13-Dec-19 |
MoRTH |
124085 |
Construction of 2-Lane ROB and its approaches in lien of level crossing No. 31 @ Km 2.100 (Railway chainage 33/900-1000) on NH-326A on EPC mode in the State of A.P.Job No. NH-326 A -AP-17-18 -670 dt 28-03-2018. |
Under Implementation |
Under Const. |
RO MoRTH Vijayawada |
NH Division KAKINADA |
RO MoRTH Vijayawada |
13-Dec-19 |
13-Dec-19 |
MoRTH |
124082 |
Construction of 2-Lane ROB and subway in lien of level crossing No. 88 at Railway km 136/5-6 between Kurbalakota & Madanapalli Section on Dharmavaram-Pakala Section at km 56/100 of NH-340 on EPC mode in the State of A.P. Job No. NH-340 -AP17-18 -669 dt 28-03-2018. |
Under Implementation |
Awarded, not Appointed |
RO MoRTH Vijayawada |
NH Division KADAPA |
RO MoRTH Vijayawada |
13-Dec-19 |
13-Dec-19 |
MoRTH |
123729 |
Rehabilitation and upgradation of New NH 544DD from design Chainage Km. 56/000 to 102/20 of Kalyandrg - Molakalmuru Section |
Under Implementation |
Under Const. |
RO MoRTH Vijayawada |
NH Division ANANTAPUR |
RO MoRTH Vijayawada |
13-Dec-19 |
13-Dec-19 |
MoRTH |
91705 |
Rehabilitation and up-gradation of NH-42 from 76/000 to Km.102/130 (Design Ch. 76/000 to 99.971 excluding Km 77.300 to 78.350) (Rapthadu to Bathalapalli section) to four lane in the State of Andhra Pradesh through EPC |
Under Implementation |
Under Const. |
RO MoRTH Vijayawada |
NH Division ANANTAPUR |
RO MoRTH Vijayawada |
13-Dec-19 |
13-Dec-19 |
MoRTH |
91702 |
Rehabilitation and upgradation of NH 326A from km 0/0 to 41/979 (excluding km 2/255 to 3/372 and km 36/820 to 38/275) (Odisha border to Narasamapeta) to two lane with paved Shoulders in the State of Andhra Pradesh under NH(O) on EPC Mode |
Under Implementation |
Under Const. |
RO MoRTH Vijayawada |
NH Division KAKINADA |
RO MoRTH Vijayawada |
13-Dec-19 |
13-Dec-19 |
MoRTH |
67828 |
Rehabilitation and up-gradation of NH-544E from Km 0/00 to Km 56/803 (Design Ch. 0/00 to 56/803) (Kodikonda Junction to Madakasira section) to two lane with paved shoulder in the State of Andhra Pradesh under NH(O) on EPC mode |
Under Implementation |
Under Const. |
RO MoRTH Vijayawada |
NH Division ANANTAPUR |
RO MoRTH Vijayawada |
13-Dec-19 |
13-Dec-19 |
MoRTH |
64836 |
Rehabilitation and upgradation of Repalle to Eeppurpalem section from Km 129/927 to Km 195/000 of NH-214A (New NH-216) to two lane with paved shoulder under NHDP-IV on EPC basis |
Under Implementation |
Under Const. |
RO MoRTH Vijayawada |
PIU,MoRT&H, Machilipatnam |
RO MoRTH Vijayawada |
13-Dec-19 |
13-Dec-19 |
MoRTH |
64835 |
Rehabilitation and Up-gradation of Pasarlapudi to Dhindi section from Km 105/170 to Km 126/510 of NH -214 (New NH -216) to two lane with paved shoulder in the state of Andhra Pradesh under NHDP-IV |
Under Implementation |
Under Const. |
RO MoRTH Vijayawada |
PIU,MoRT&H, Machilipatnam |
RO MoRTH Vijayawada |
13-Dec-19 |
13-Dec-19 |
MoRTH |
64834 |
Rehabilittion and upgradation of Machilipatnam to Avanigadda section from km 84/550 - 124/200 of NH 214A (new NH 216) to two lane with paved shoulder in the State of AP under NHDPIV through EPC basis |
Under Implementation |
Under Const. |
RO MoRTH Vijayawada |
PIU,MoRT&H, Machilipatnam |
RO MoRTH Vijayawada |
13-Dec-19 |
13-Dec-19 |
MoRTH |
64831 |
Rehabilitation and Up-gradation of Thimmapuram to Gurajanapalli section from Km 26/150 to Km 41/161 of NH - 214 ( New NH - 216) to two lane with paved shoulder in the state of Andhra Pradesh under NHDP-IV |
Under Implementation |
Under Const. |
RO MoRTH Vijayawada |
PIU,MoRT&H, Machilipatnam |
RO MoRTH Vijayawada |
13-Dec-19 |
13-Dec-19 |
MoRTH |
60529 |
Rehabilitation and up-gradation of NH-75(Old NH-234) from Km 506/100 to Km 508/700 and Km 518/700 to Km 534/350 (Design Ch. Km 506/100 to 508/650 and 518/700 to 534/100) Mangalore to Thiruvannamalai Road to two lane with paved shoulders in the State of Andhra Pradesh on EPC mode |
Under Implementation |
Under Const. |
RO MoRTH Vijayawada |
NH Division Chittor |
RO MoRTH Vijayawada |
13-Dec-19 |
13-Dec-19 |
MoRTH |
60528 |
Rehabilitation and upgradation of NH-67 from Km 424/650 to Km 487/693( Gooty-Tadipatri-District Border section) to two lane with paved shoulders in the State of Andhra Pradesh under Corridor Approach through EPC Basis Contract |
Under Implementation |
Under Const. |
RO MoRTH Vijayawada |
NH Division ANANTAPUR |
RO MoRTH Vijayawada |
13-Dec-19 |
13-Dec-19 |
MoRTH |
60527 |
Rehabilitation and up-gradation of NH-167 from Km 14/900 to Km70/000 (Design Ch. 14/900 to 69/700) (Chintakunta to Adoni section) to two lane with paved shoulders in the State of Andhra Pradesh under Corridor Approach through Engineering, Procurement & Co |
Under Implementation |
Under Const. |
RO MoRTH Vijayawada |
NH Division KURNOOL |
RO MoRTH Vijayawada |
13-Dec-19 |
13-Dec-19 |
MoRTH |
60247 |
Rehabilitation and up-gradation of NH-42 from km 244/930 to km 299/775 (Madanapalli-Punganuru-Palamaneru Section) to two lane with paved shoulder in the state of Andhra Pradesh under Corridor Scheme on EPC Mode |
Under Implementation |
Under Const. |
RO MoRTH Vijayawada |
NH Division Chittor |
RO MoRTH Vijayawada |
13-Dec-19 |
13-Dec-19 |
MoRTH |
52029 |
Rehabilitation and upgradation of Gurajanapalli village - Polekuru village section (from km.41/161 to 59/800) and Komaragigi-pasarlapudi section (km 70/400 to 105/170) of NH-214 (new NH-216) to two lane with paved shoulder in the state of Andhra Prad |
Under Implementation |
Under Const. |
RO MoRTH Vijayawada |
PIU,MoRT&H, Machilipatnam |
RO MoRTH Vijayawada |
13-Dec-19 |
13-Dec-19 |
MoRTH |
52028 |
Rehabilitation and up-gradation of Karnataka/Andhra Border to Gooty section from Km.368/920 to Km. 424/225 of NH-67 to four lane with paved shoulder in the state of Andhra Pradesh under NHDP-IV on EPC basis |
Under Implementation |
Under Const. |
RO MoRTH Vijayawada |
NH Division ANANTAPUR |
RO MoRTH Vijayawada |
13-Dec-19 |
13-Dec-19 |
MoRTH |
52025 |
Rehabilitation and Up-gradation of Dhindi - Digamarru section from Km 126/510 to Km 135/740 of NH -214(New NH -216) and digamarru -Losari section from Km 0/000 tp Km 34/230 of NH-214 A(New Nh-216) to two lane with paved shoulder in the state of AP-NH |
Under Implementation |
Under Const. |
RO MoRTH Vijayawada |
PIU,MoRT&H, Machilipatnam |
RO MoRTH Vijayawada |
13-Dec-19 |
13-Dec-19 |
MoRTH |
52024 |
4 laning of 5.122 km of NH9(New NH69) from Km 269/900 (Des.Ch.0/0) to km275/622(Des.Ch.5/122)i.e.connecting of NH9 (1.4 km) with NH5 (3.6 km) including 6 lane Elevated fly over from Bhavanipuram to Kanakadurgamma Varadhi in Vijayawada |
Under Implementation |
Under Const. |
RO MoRTH Vijayawada |
NH Division VIJAYAWADA |
RO MoRTH Vijayawada |
13-Dec-19 |
13-Dec-19 |
MoRTH |
52023 |
Rehabilitation & Upgradation of NH214(New NH-216) from Km 34/230 to Km 84/550 (Losari to Machavaram Section) to two lane with paved shoulder in the state of Andhrapradesh under NHDP-IV through Engineering, Procurement& Construction (EPC) mode. |
Under Implementation |
Under Const. |
RO MoRTH Vijayawada |
PIU,MoRT&H, Machilipatnam |
RO MoRTH Vijayawada |
13-Dec-19 |
13-Dec-19 |
MoRTH |
52017 |
Construction of 4-lane ROB in lieu of LC No.122 at km 160/800 Chittor - Kurnool road NH-18 (New NH-40) |
Under Implementation |
Under Const. |
RO MoRTH Vijayawada |
NH Division KADAPA |
RO MoRTH Vijayawada |
13-Dec-19 |
13-Dec-19 |
MoRTH |
52015 |
Rehabilitation and Upgradation of NH-219 from km.58/600 to 140/680 (Palamaneru to Krishnagiri Border Section) to two lane with paved shoulders in the State of AP under Corridor Aproach on EPC mode |
Under Implementation |
Under Const. |
RO MoRTH Vijayawada |
NH Division Chittor |
RO MoRTH Vijayawada |
13-Dec-19 |
13-Dec-19 |
MoRTH |
52004 |
Construction of proposed 4-lane ROB and its approaches in lieu of existing Level Crossing No.23/SPL class at Km 3.6 on NH-18 between Chittoor & RVS Nagar railway stations on Chittoor - Pakala Railway section in the state of Andhra Pradesh on EPC |
Under Implementation |
Under Const. |
RO MoRTH Vijayawada |
NH Division Chittor |
RO MoRTH Vijayawada |
13-Dec-19 |
13-Dec-19 |
MoRTH |
50614 |
Construction of ROB on NH-81 at Km 48 |
Under Implementation |
Under Const. |
RO MoRTH Patna |
NH Division Purnea |
RO MoRTH Patna |
11-Dec-19 |
11-Dec-19 |
MoRTH |
50600 |
Construction of ROB on NH-81 at Km 31 |
Under Implementation |
Under Const. |
RO MoRTH Patna |
NH Division Purnea |
RO MoRTH Patna |
11-Dec-19 |
11-Dec-19 |
MoRTH |
123282 |
Widening to four lane and Strenthening in selected strech of Ahmedabad-Dandi (Package 2, 6km ) Route from KM 71/200 to KM 77/600 of N.H. 64 i.e. Nadiad DDIT - Uttarsanda-Bhumel in the state of Gujarat. NH No.: 64 (Old NH-228) |
Under Implementation |
Under Const. |
RO MoRTH Gandhinagar |
NH Division Varodara |
NH Division Varodara |
9-Dec-19 |
25-Oct-19 |
MoRTH |
58460 |
Improvement of road safety through foothpaths, drains , improvements of junctions, road signs/ marking etc . in Anand city limits from km 85/600 to 90/300 NH-64 (Old NH-228) in the state of Gujarat |
Under Implementation |
Under Const. |
RO MoRTH Gandhinagar |
NH Division Varodara |
NH Division Varodara |
9-Dec-19 |
25-Oct-19 |
MoRTH |
144355 |
Strengthening of 2-lane with paved shoulder of NH-54 from 12th km to 40th km under Annual plan for the year 2018-19 on EPC mode PWD, NH Division, Silchar in the State of Assam. (Job No. 054/AS/2018-19/184) |
Under Implementation |
Awarded, not Appointed |
RO MoRTH Guwahati |
NH Division Silchar |
NH Division Silchar |
6-Dec-19 |
28-Nov-19 |
MoRTH |
50693 |
Construction of Silchar bypass on NH-53 in Assam |
Under Implementation |
Under Const. |
RO MoRTH Guwahati |
NH Division Silchar |
NH Division Silchar |
6-Dec-19 |
28-Nov-19 |
MoRTH |
52375 |
Re-Construction of a new bridge across river Tarapur at ch-270.15 km of NH-60 in the District of Bankura, West Bengal Job No-NH-60 / (WB)/ (15)/ 15-16-009-S&R (B) |
Under Implementation |
Under Const. |
RO MoRTH Kolkata |
NH Division-III |
NH Division-III |
5-Dec-19 |
17-Oct-19 |
MoRTH |
52376 |
Re-Construction of a new bridge across river Shali at ch- 247.00 km of NH-60 in the District of Bankura, West Bengal |
Under Implementation |
Under Const. |
RO MoRTH Kolkata |
NH Division-III |
NH Division-III |
5-Dec-19 |
17-Oct-19 |
MoRTH |
58474 |
Construction of ROB and its approaches in lieu of Unmanned Level Crossing at km 303.9 on NH-60 |
Under Implementation |
Awarded, not Appointed |
RO MoRTH Kolkata |
NH Division-III |
NH Division-III |
5-Dec-19 |
17-Oct-19 |
MoRTH |
58471 |
Construction of ROB and its approaches in lieu of level crossing No. KA-61 at km 194.850 of NH-60. |
Under Implementation |
Under Const. |
RO MoRTH Kolkata |
NH Division-III |
NH Division-III |
5-Dec-19 |
17-Oct-19 |
MoRTH |
58473 |
Construction of ROB and its approaches in lieu of Level Crossing No. 6/B/T at km 284.170 on NH-60 |
Under Implementation |
Under Const. |
RO MoRTH Kolkata |
NH Division-III |
NH Division-III |
5-Dec-19 |
17-Oct-19 |
MoRTH |
134727 |
"Reconstruction of minor bridges at chainage 181.868 km of NH-60 in the district Bankura ,West Bengal under EPC mode. Job No. 060-wb-2018-19/430" |
Under Implementation |
Under Const. |
RO MoRTH Kolkata |
NH Division-III |
NH Division-III |
5-Dec-19 |
17-Oct-19 |
MoRTH |
64832 |
Development of alignment of Fulahar Bridge approach on newly declared NH-131A from Chainage 49+05 Km to 51+20 Km and from 53+81 Km to 55+19 Km in the district Malda. Job No.- 131A-WB-2016-17/416 |
Under Implementation |
Under Const. |
RO MoRTH Kolkata |
NH Division-VII |
NH Division-VII |
5-Dec-19 |
17-Oct-19 |
MoRTH |
64849 |
Construction of 2 lane with paved shoulder from Km. 168.00 to 183.783 (Yesemyong to Unger) on Mokokchung to Tuli Section of NH-61 under EPC mode in the State of Nagaland. |
Under Implementation |
Under Const. |
RO MoRTH Guwahati |
EE Div-II |
EE Div-II |
4-Dec-19 |
28-Nov-19 |
MoRTH |
55596 |
Strengthening and widening to two lane with paved shoulder of NH-61 from Km. 40.00 to Km 72.40under EPC mode in the State of Nagaland during 2016-17(package-II from km 56.00 to km 72.40) |
Under Implementation |
Under Const. |
RO MoRTH Guwahati |
EE Div-I |
EE Div-I |
4-Dec-19 |
28-Nov-19 |
MoRTH |
53076 |
Strengthening and widening to two lane with paved shoulder of NH-61 from Km 40.00 to Km 72.40 under EPC mode in the State of Nagaland during FY 2016-17 (package-I from km 40.00 to km 56.00) |
Under Implementation |
Under Const. |
RO MoRTH Guwahati |
EE Div-I |
EE Div-I |
4-Dec-19 |
28-Nov-19 |
MoRTH |
122534 |
Improvement of City Portion of Dimapur and Kohima city of NH-39 (Package-I Dimapur City Km 106.90 to Km 124.20) |
Under Implementation |
Under Const. |
RO MoRTH Guwahati |
EE Div-I |
EE Div-I |
4-Dec-19 |
28-Nov-19 |
MoRTH |
123135 |
Strengthening profile correction and re-designing of pavement on NH-102B from km 25.50 to km 37.10 (saichal to Hliappui) and from km 46.10 to km 76.10 (pawlrang to Ngopa) in the State of Mizoram during 2017-18 |
Under Implementation |
Under Const. |
RO MoRTH Guwahati |
NH Division-3, Mizoram |
NH Division-3, Mizoram |
28-Nov-19 |
28-Nov-19 |
MoRTH |
55523 |
Construction for 2-laning with paved shoulder of NH-150 of stretch from Km 42/800 - Km 60/300 |
Under Implementation |
Under Const. |
RO MoRTH Guwahati |
NH Division-2, Mizoram |
NH Division-2, Mizoram |
28-Nov-19 |
28-Nov-19 |
MoRTH |
50647 |
Construction of a new 2-lane highway from km 38/00 to 71/00 in Mizoram to support Kaladan Multi Modal Transit Transport Project in Phase 'A' of SARDP-NE ( Package MM-II) |
Under Implementation |
Under Const. |
RO MoRTH Guwahati |
Multi-Model Project Division-II |
Multi-Model Project Division-II |
28-Nov-19 |
28-Nov-19 |
MoRTH |
124187 |
Strengthening from Km. 64/000 to Km. 69/000, 90/760 to 119/000 and Km. 126/000 to Km. 160/000 (Length=67.804 Km) of NH-36 for the year 2017-18 under Bakulia NH Division, Diphu in the state of Assam. (Job No. 036/AS/2017-18/176) |
Under Implementation |
Under Const. |
RO MoRTH Guwahati |
Bakulia NH Division |
Bakulia NH Division |
28-Nov-19 |
28-Nov-19 |
MoRTH |
55559 |
Strengthening with paved shoulder from km 30/0 to km 46/0, km 54/0 to km 61/0, km 69/0 to km 80/0 and km 80/0 to km 96/0 of NH-39 for the year 2015-16 including toll plaza (Job No.039-AS-2016-17-153) |
Under Implementation |
Under Const. |
RO MoRTH Guwahati |
Golaghat NH Division |
Golaghat NH Division |
28-Nov-19 |
28-Nov-19 |
MoRTH |
144359 |
Strengthening of pavement from km 61.00 to km 69.00 and widening of 1.5 m paved shoulder on either side and strengthening from km 103.00 to km 106.00 of NH-39 under Annual plan for the year 2018-19 under Golaghat NH Division, in the State of Assam on EPC mode (Job No. 039/AS/2018-19/186) |
Under Implementation |
Awarded, not Appointed |
RO MoRTH Guwahati |
Golaghat NH Division |
Golaghat NH Division |
28-Nov-19 |
28-Nov-19 |
MoRTH |
102109 |
Raising and strengthening including providing road side stone masonry longitudinal covered drain at Km. 107th of NH-39 under Golaghat NH Division, Golaghat under Annual Plan for the year 2017-18 in the state of Assam. (Job No. 039/AS/2017-18/174) |
Under Implementation |
Under Const. |
RO MoRTH Guwahati |
Golaghat NH Division |
Golaghat NH Division |
28-Nov-19 |
28-Nov-19 |
MoRTH |
55572 |
Strengthening of existing road from km. 653.364- 668,668.608 -690.329 of NH-37 (L=18.357 km), &construction of masonry drain under AP 2016-17 under NH Division, Dibrugarh in the State of Assam |
Under Implementation |
Under Const. |
RO MoRTH Guwahati |
NH Division Dibrugarh |
NH Division Dibrugarh |
28-Nov-19 |
28-Nov-19 |
MoRTH |
50690 |
Construction os 2-lane NH-37 with paved shoulders from end of ROB at Makum to NH-52 near Rupai (length=23.482km) under Dibrugarh NH Division SARDP-NE/NH-37/PWD/AS/2010-11/165 |
Under Implementation |
Under Const. |
RO MoRTH Guwahati |
NH Division Dibrugarh |
NH Division Dibrugarh |
28-Nov-19 |
28-Nov-19 |
MoRTH |
50646 |
Construction of a new - 2 Lane Highway from Km 0.00 (on NH-54 near Lawngtlai) to Km 38.00 (Crossing with GS Road) (Length=38 Km) in Mizoram to support Kaladan Multi Modal Transit Transport Project in Phase ‘A’ of SARDP-NE in the state of Mizoram |
Under Implementation |
Under Const. |
RO MoRTH Guwahati |
Multi-Model Project Division-I, Mizoram |
Multi-Model Project Division-I, Mizoram |
28-Nov-19 |
28-Nov-19 |
MoRTH |
50687 |
Construction of 2-lane Highway with paved shoulders between Dibrugarh - Panitola km 603/0 to 637/0 of NH-37 |
Under Implementation |
Under Const. |
RO MoRTH Guwahati |
NH Division Dibrugarh |
NH Division Dibrugarh |
28-Nov-19 |
28-Nov-19 |
MoRTH |
50686 |
2 laning from Kanubari to start of Bogibeel Bridge |
Under Implementation |
Under Const. |
RO MoRTH Guwahati |
NH Division Dibrugarh |
NH Division Dibrugarh |
28-Nov-19 |
28-Nov-19 |
MoRTH |
50699 |
Strengthening and widening of NH-44 from km. 206/500 to km. 222/00, km. 222/00 to km. 223/000, 247/000 to km. 252/280 and km. 263/191(Ex. Ch. 261/761 km.) to km. 272/241(Ex. |
Under Implementation |
Under Const. |
RO MoRTH Guwahati |
NH Division Karimganj |
NH Division Karimganj |
28-Nov-19 |
28-Nov-19 |
MoRTH |
50696 |
Katlicherra bypass from km. 47.00 - 52.00 |
Under Implementation |
Under Const. |
RO MoRTH Guwahati |
NH Division Karimganj |
NH Division Karimganj |
28-Nov-19 |
28-Nov-19 |
MoRTH |
50695 |
Dhaleshwari Bypass from km. 0.00 - 3.500 |
Under Implementation |
Under Const. |
RO MoRTH Guwahati |
NH Division Karimganj |
NH Division Karimganj |
28-Nov-19 |
28-Nov-19 |
MoRTH |
50700 |
Construction of 2-lane Patherkandi Bypass Job No.-044/AS/2014-15/122 |
Under Implementation |
Under Const. |
RO MoRTH Guwahati |
NH Division Karimganj |
NH Division Karimganj |
28-Nov-19 |
28-Nov-19 |
MoRTH |
148492 |
Special Repair to Bailey Bridge at Km 135/80 (R.Luaklui) & 136/50 (R.Luakzal) of NH-150 in the state of Mizoram. (Job No. TA/150/MZ/2015-16/84) |
Under Implementation |
Under Const. |
RO MoRTH Guwahati |
NH Division-2, Mizoram |
RO MoRTH Guwahati |
28-Nov-19 |
28-Nov-19 |
MoRTH |
145955 |
Repair and rehabilitation of existing pavement from km 110.00 to km 150.00 on NH-6 (Kawlkulh to Champai) in the State of Mizoram during 2018-19 on EPC mode. (Job No. 006/MZ/2018-19/117) |
Under Implementation |
Awarded, not Appointed |
RO MoRTH Guwahati |
NH Division-3, Mizoram |
RO MoRTH Guwahati |
28-Nov-19 |
28-Nov-19 |
MoRTH |
145951 |
Repair and rehabilitation of existing pavement from km 35.00 to km 80.00 on NH-6 (Keifand to Kawlkulh) in the State of Mizoram during 2018-19 on EPC mode. (Job No. 006/MZ/2018-19/116) |
Under Implementation |
Awarded, not Appointed |
RO MoRTH Guwahati |
NH Division-3, Mizoram |
RO MoRTH Guwahati |
28-Nov-19 |
28-Nov-19 |
MoRTH |
144357 |
Strengthening of existing 2-lane from km 445.00 to km 455.00 & km 475.00 to km 500.00 (Total Length = 35.00)of NH-52(New NH-15) under Annual plan for the year 2018-19 under Nagaon NH Division, Nagaon in the State of Assam on EPC mode (Job No. 052(New NH-15)/AS/2018-19/185) |
Under Implementation |
Awarded, not Appointed |
RO MoRTH Guwahati |
NH Division Nagaon |
RO MoRTH Guwahati |
28-Nov-19 |
28-Nov-19 |
MoRTH |
142854 |
Strengthening of existing pavement from km 15.35 to km 30.00 of NH-137A Imphal - Kakching Lamkhai section in the state of Manipur on EPC mode. (Job No. 137A/MN/2018-19/29) |
Under Implementation |
Awarded, not Appointed |
RO MoRTH Guwahati |
NH-Division No I Manipur |
RO MoRTH Guwahati |
28-Nov-19 |
28-Nov-19 |
MoRTH |
124230 |
Widening of Bridges No.3/1, 6/1, 8/1, 12/1, 17/1, 19/1, & 29/1 on NH-52 under Annual Plan under Rangia NH Division in the State of Assam. (Job No. 015/AS/2017-18/181) |
Under Implementation |
Under Const. |
RO MoRTH Guwahati |
NH Division Rangia |
RO MoRTH Guwahati |
28-Nov-19 |
28-Nov-19 |
MoRTH |
123131 |
Rehabilitation of distress bridges at Ch. 91.60 Km, Ch. 94.60 Km, Ch. 97.40 Km, Ch. 117.90 Km, 124.60 Km, Ch. 138.80 Km, Ch. 169.70 Km, Ch. 171.10 Km, Ch. 178.00 Km, Ch. 180.20 Km, Ch. 180.40 Km, Ch. 182.60 Km, Ch. 188.50 Km, on NH-62 in the state of Meghalaya.Job No. 062/MG/2016-17/150 |
Under Implementation |
Under Const. |
RO MoRTH Guwahati |
NH Division Baghmara |
RO MoRTH Guwahati |
28-Nov-19 |
28-Nov-19 |
MoRTH |
80707 |
Installation of crash barriers on various streches of national Highways in the state of Mizoram. Job No. NHs-MZ-2016-17-RSCE-031 |
Under Implementation |
Under Const. |
RO MoRTH Guwahati |
NH Division-1, Mizoram |
RO MoRTH Guwahati |
28-Nov-19 |
28-Nov-19 |
MoRTH |
67902 |
Improvement of City portion of Kohima and Dimapur City of Nh-39 in the State of Nagaland under EPC mode during 2016-17 (Package-II Kohima City from Km 177.60 to Km 187.60) |
Under Implementation |
Under Const. |
RO MoRTH Guwahati |
EE Div-I |
RO MoRTH Guwahati |
28-Nov-19 |
28-Nov-19 |
MoRTH |
67328 |
Reconstruction of 6 nos. of weak SPT Bridges with bailey Bridges including approaches (Br. No 181/2, 174/4,201/7 etc) on NH-62 (Job No: 062/MG/2016-17/142) Length (Km - 195.40) |
Under Implementation |
Under Const. |
RO MoRTH Guwahati |
NH Division Baghmara |
RO MoRTH Guwahati |
28-Nov-19 |
28-Nov-19 |
MoRTH |
67323 |
Reconsttrucion of Weak Culverts Nos. 139/4, 142/2, 158/2,158/6 etc. on NH-62 including Retaining Wall, unlined drains in Meghalaya (Job No: 062/MG/2016-17/141) Length (Km - 195.40) |
Under Implementation |
Under Const. |
RO MoRTH Guwahati |
NH Division Baghmara |
RO MoRTH Guwahati |
28-Nov-19 |
28-Nov-19 |
MoRTH |
55565 |
Strengthening with paved shoulders in Km 13 to 15, Km 20 to 23, Km 35 and Km 36th and Km 57 to 63rd (Total length=16.870 Km) ubnder Rangia NH |
Under Implementation |
Under Const. |
RO MoRTH Guwahati |
NH Division Rangia |
RO MoRTH Guwahati |
28-Nov-19 |
28-Nov-19 |
MoRTH |
55506 |
Strengthening of existing two lane pavements i/c paved shoulder on NH No. 150 from Km 433.00 to Km 454.798 |
Under Implementation |
Under Const. |
RO MoRTH Guwahati |
NH-Division No III Manipur |
RO MoRTH Guwahati |
28-Nov-19 |
28-Nov-19 |
MoRTH |
55505 |
Strengthening of existing two lane pavements i/c paved shoulder on NH No. 150 from Km 412.00 to Km 433.00 |
Under Implementation |
Under Const. |
RO MoRTH Guwahati |
NH-Division No III Manipur |
RO MoRTH Guwahati |
28-Nov-19 |
28-Nov-19 |
MoRTH |
55500 |
Widening 4-lane to 6-lane from Km 454.798 to Km 459.600 and Widening of formation from Km 474.00 to Km 488.00 and construction of Paved shoulder from Km 467.00 to Km 474.00 |
Under Implementation |
Under Const. |
RO MoRTH Guwahati |
NH-Division No III Manipur |
RO MoRTH Guwahati |
28-Nov-19 |
28-Nov-19 |
MoRTH |
53061 |
Paikan-Dalu |
Under Implementation |
Under Const. |
RO MoRTH Guwahati |
NH Cum Tura Central Division |
RO MoRTH Guwahati |
28-Nov-19 |
28-Nov-19 |
MoRTH |
53046 |
Construction of 1.50 m wide paved shoulder on eighter side of 10 km stretch from km 308.00 to km 318.00 along with widening of intermediate lane to 2-lane from km 313.00 to km 318.00 on Churaibari - Agartala Section of NH -8 (old NH -44) in Tripura. |
Under Implementation |
Under Const. |
RO MoRTH Guwahati |
NH-Division Kumarghat |
RO MoRTH Guwahati |
28-Nov-19 |
28-Nov-19 |
MoRTH |
53029 |
Construction of longitudinal drains at stretches from 134/00 to km 146/300 |
Under Implementation |
Under Const. |
RO MoRTH Guwahati |
NH Division Guwahati |
RO MoRTH Guwahati |
28-Nov-19 |
28-Nov-19 |
MoRTH |
50711 |
2 Laning of Lumding-Diphu-Manja Road, Haflong-Jatinga Road, Baska-Barama Road, Morigaon-Jagiroad Road, Kokrajhar-Karigaon Road and Udalguri-Routa Road in the state of Assam (Length = 146km) under SARDP-NE, Phase A in the state of Assam (Job No. SARDP |
Under Implementation |
Under Const. |
RO MoRTH Guwahati |
NH Division Nagaon |
RO MoRTH Guwahati |
28-Nov-19 |
28-Nov-19 |
MoRTH |
50707 |
Construction of Proposed North Lakhimpur By-pass from existing km 338/924 to km 349/213 of NH-52 in the state of Assam (Job No.052-AS-2011-12-099) |
Under Implementation |
Under Const. |
RO MoRTH Guwahati |
NH Division Nagaon |
RO MoRTH Guwahati |
28-Nov-19 |
28-Nov-19 |
MoRTH |
50698 |
2 laning of Goalpara- Solmari road/189 |
Under Implementation |
Under Const. |
RO MoRTH Guwahati |
NH Division Guwahati |
RO MoRTH Guwahati |
28-Nov-19 |
28-Nov-19 |
MoRTH |
50649 |
Widening to 2-Lane, re-alignment and geometric improvement from Km 11/00 to Km 114/618 of NH 44 A |
Under Implementation |
Under Const. |
RO MoRTH Guwahati |
NH Division-1, Mizoram |
RO MoRTH Guwahati |
28-Nov-19 |
28-Nov-19 |
MoRTH |
50648 |
Construction of a new 2-lane highways from km 71/00 to km 99/83 in Mizoram to support Kaladan Multi Modal Transit Transport Project in SARDP NE PhaseA |
Under Implementation |
Under Const. |
RO MoRTH Guwahati |
Multi-Model Project Division-II |
RO MoRTH Guwahati |
28-Nov-19 |
28-Nov-19 |
MoRTH |
61096 |
Strengthening of road stretches along with provision for Retaining walls, Breast walls & hillside drains from 0.00 km to 4.40 km & from 14.0 km to 28.0 km of NH-10 in SBD mode (Job 408) |
Under Implementation |
Under Const. |
RO MoRTH Kolkata |
NH Division-IX |
NH Division-IX |
11-Nov-19 |
17-Oct-19 |
MoRTH |
52356 |
Rehabilitation of landslide location with slope protection and drainage improvement at Tindharia on NH 55 (km 50 + 155 to 50 + 182, km 52+ 650 to Km 52+ 800 and Km 53 +452 to km 53+ 475) |
Under Implementation |
Under Const. |
RO MoRTH Kolkata |
NH Division-IX |
NH Division-IX |
11-Nov-19 |
17-Oct-19 |
MoRTH |
52319 |
Rehabilitation of landslide location along with slope protection and drainage improvement at Paglajhora on NH-55 (km 43+500 to 43+950) |
Under Implementation |
Under Const. |
RO MoRTH Kolkata |
NH Division-IX |
NH Division-IX |
11-Nov-19 |
17-Oct-19 |
MoRTH |
58475 |
Construction of twins 2-lane ROB and its approaches in replacement of Level Crossing at km 615.5 of NH-31 |
Under Implementation |
Under Const. |
RO MoRTH Kolkata |
NH Division-IX |
NH Division-IX |
11-Nov-19 |
17-Oct-19 |
MoRTH |
58476 |
Construction of twins 2-lane ROB and its approached in liue of Level Crossing at km 652.6 of NH-31 |
Under Implementation |
Under Const. |
RO MoRTH Kolkata |
NH Division-IX |
NH Division-IX |
11-Nov-19 |
17-Oct-19 |
MoRTH |
58477 |
Construction of ROB and its approaches in lieu of Level Crossing at km 661.100 on NH-31 |
Under Implementation |
Under Const. |
RO MoRTH Kolkata |
NH Division-IX |
NH Division-IX |
11-Nov-19 |
17-Oct-19 |
MoRTH |
64837 |
Upgradation of NH-31C with a minimum of 2-lane with paved shoulder configuration starting from km 105.000 to km 145.632 (total length 40.632 km) in Jalpaiguri on EPC mode Job-417) |
Under Implementation |
Under Const. |
RO MoRTH Kolkata |
NH Division-IX |
NH Division-X |
11-Nov-19 |
17-Oct-19 |
MoRTH |
52352 |
Rehabilitation & upgradation of Pundibari to Baxirhat from Km 770 to Km 814. |
Under Implementation |
PCOD |
RO MoRTH Kolkata |
NH Division-X |
NH Division-X |
11-Nov-19 |
17-Oct-19 |
MoRTH |
123147 |
Strengthening of NH - 60 from Ch. 401.00 Km. (Nalhati) to 422.450 Km. (Moregram) along with Improvement of Shoulder in the districts of Birbhum and Murshidabad in the State of West Bengal under AP-2017-18 (Job No. 060-WB-2017-18/427). |
Under Implementation |
Under Const. |
RO MoRTH Kolkata |
NH Division-XII |
NH Division-XII |
11-Nov-19 |
17-Oct-19 |
MoRTH |
143021 |
Improvement of NH-60 from km 330.00 to km 355.00 & from km 360.00 to km 374.00 except the stretch from km 337.703 to km 339.046 (for Suri ROB) by way of Strengthening of existing carriageway and laying of wearing course from km 355.00 to km 360.00 in the district of Birbhum, West Bengal under EPC mode . Job No.060-WB-2018-19/433 |
Under Implementation |
Under Const. |
RO MoRTH Kolkata |
NH Division-XII |
NH Division-XII |
11-Nov-19 |
17-Oct-19 |
MoRTH |
58484 |
Construction of ROB and its approaches in lieu of LC No. 10/B/T at Km 307.050 of NH-60. |
Under Implementation |
Awarded, not Appointed |
RO MoRTH Kolkata |
NH Division-XII |
NH Division-XII |
11-Nov-19 |
17-Oct-19 |
MoRTH |
58485 |
Construction of ROB and its appraoches in lieu of LC no.21/SPL/E at Km 338.000 on NH-60 |
Under Implementation |
Awarded, not Appointed |
RO MoRTH Kolkata |
NH Division-XII |
NH Division-XII |
11-Nov-19 |
17-Oct-19 |
MoRTH |
52351 |
Construction of PSC Girder bridge over river Sal & Hinglow in place of damaged vented causeway at Km 314.330 & Km 309.800 of NH-60 |
Under Implementation |
Under Const. |
RO MoRTH Kolkata |
NH Division-XII |
NH Division-XII |
11-Nov-19 |
17-Oct-19 |
MoRTH |
134725 |
"Rehabilitation of 9 (Nine) damaged Bridges/ROB along NH-60 during the year of 2018-19 Iin the district of Birbhum. Job No.060-WB-2018-19/429" |
Under Implementation |
Under Const. |
RO MoRTH Kolkata |
NH Division-XII |
NH Division-XII |
11-Nov-19 |
17-Oct-19 |
MoRTH |
148525 |
Construction of Fly Over (Bridges) at 03 major 4- arm junciton at three places Ring road junctions A B & G Ch. 10/3, 13/3 & 14/6 by passing in the alignment of newly of newly declared NH 848 A in UT of DNH on EPC mode. |
Under Implementation |
Under Const. |
RO MoRTH Gandhinagar |
NH Division Silvasa |
RO MoRTH Gandhinagar |
25-Oct-19 |
25-Oct-19 |
MoRTH |
148524 |
Upgradation Strengthening for the road stretch from Dadra to Tighra (Ch. 4/800 to 7/339 Km) and Samaravrni to Rakholi Bridge (Ch. 14/500 to 19/500 Km.) of NH 848 A at Silvassa, Dadra & Nagar Haveli UT (on EPC mode) |
Under Implementation |
Under Const. |
RO MoRTH Gandhinagar |
NH Division Silvasa |
RO MoRTH Gandhinagar |
25-Oct-19 |
25-Oct-19 |
MoRTH |
147690 |
Strengthening to A'bad-Dandi between Km 63/770 to 71/200 section (Dabhan-Nadiad city-DDIT Road) on NH-64 in the state of Gujarat on EPC basis. |
Under Implementation |
Under Const. |
RO MoRTH Gandhinagar |
NH Division Varodara |
RO MoRTH Gandhinagar |
25-Oct-19 |
25-Oct-19 |
MoRTH |
58455 |
Widening up to P.S.S. & Strengthening to Km. 0/0 to 11/0 (Una - Delvada) |
Under Implementation |
PCOD |
RO MoRTH Gandhinagar |
NH Division Rajkot |
RO MoRTH Gandhinagar |
25-Oct-19 |
25-Oct-19 |
MoRTH |
144112 |
"Improvement of Riding Quality (IRQ) from km 654.00 to km 670.00 of NH-31 in the district of Jalpaiguri, West Bengal during the year 2018-19 on EPC mode. (Job No.- 031-WB-2018-19/437)" |
Under Implementation |
Under Const. |
RO MoRTH Kolkata |
NH Division-IX |
RO MoRTH Kolkata |
17-Oct-19 |
17-Oct-19 |
MoRTH |
148716 |
Road Safety works with Crash barrier, Parapet, Delinaters & road Protection work Hill Side & Valley Side etc from Km 5.00 to 77.10 on NH-309B in the State of Uttarakhand under Annual Plan 2018-19 |
Under Implementation |
Awarded, not Appointed |
RO MoRTH Dehradun |
NH Division Ranikhet |
RO MoRTH Dehradun |
12-Oct-19 |
12-Oct-19 |
MoRTH |
148714 |
Construction of 24 M Span RCC girder Bridge in km 7.00(H.M. 6-8) NH-309A in the State of Uttarakhand under Annual Plan 2018-19 |
Under Implementation |
Awarded, not Appointed |
RO MoRTH Dehradun |
NH Division Lohaghat |
RO MoRTH Dehradun |
12-Oct-19 |
12-Oct-19 |
MoRTH |
148713 |
Construction of drain & laying of interlocking tiles in Km. 18, 21, 27 & 28 in populated area. |
Under Implementation |
Under Const. |
RO MoRTH Dehradun |
NH Division Haldwani |
RO MoRTH Dehradun |
12-Oct-19 |
12-Oct-19 |
MoRTH |
148712 |
Protection work in km 4.00 to 63.00 on NH-121(309) in NH-87 (New NH-109) under NH(O) 2018-19 in the State of Uttarakhand under Annual Plan 2018-19 |
Under Implementation |
Under Const. |
RO MoRTH Dehradun |
NH Division Haldwani |
RO MoRTH Dehradun |
12-Oct-19 |
12-Oct-19 |
MoRTH |
148710 |
Restoration and protection work in km 89.100 to 123.000 in NH-87 (New NH-109) under NH(O) 2018-19 in the State of Uttarakhand under Annual Plan 2018-19 |
Under Implementation |
Under Const. |
RO MoRTH Dehradun |
NH Division Haldwani |
RO MoRTH Dehradun |
12-Oct-19 |
12-Oct-19 |
MoRTH |
148708 |
Protection work in km 92.100 to 123.000 in NH-87 (New NH-109) under NH(O) 2018-19 in the State of Uttarakhand under Annual Plan 2018-19 |
Under Implementation |
Under Const. |
RO MoRTH Dehradun |
NH Division Haldwani |
RO MoRTH Dehradun |
12-Oct-19 |
12-Oct-19 |
MoRTH |
148707 |
Protection work in km. 150.00 To 165.00 on NH-119(new No. 534) |
Under Implementation |
Awarded, not Appointed |
RO MoRTH Dehradun |
NH Division Dhumakot |
RO MoRTH Dehradun |
12-Oct-19 |
12-Oct-19 |
MoRTH |
148706 |
Strengthening work from Km 70.00 to Km 78.00 on NH-121 in state of Uttarakhand |
Under Implementation |
Awarded, not Appointed |
RO MoRTH Dehradun |
NH Division Dhumakot |
RO MoRTH Dehradun |
12-Oct-19 |
12-Oct-19 |
MoRTH |
148704 |
Construction of 4 Nos bridges viz 24 m span bridge at km. 121 & km. 138, 42 m span bridge at km. 141 and 10 m span bridge at km. 149 on NH-121 (New No. 309) in the State of Uttarakhand |
Under Implementation |
Awarded, not Appointed |
RO MoRTH Dehradun |
NH Division Dhumakot |
RO MoRTH Dehradun |
12-Oct-19 |
12-Oct-19 |
MoRTH |
148703 |
Construction of 5 Nos bridges viz 30 m span bridge at km. 152, 12 m span bridge at km. 156, 42 m span bridge at km. 158, 30 m span bridge at km. 163 and 24 m span bridge at km. 165 on NH-121 (New No. 309) in the State of Uttarakhand |
Under Implementation |
Awarded, not Appointed |
RO MoRTH Dehradun |
NH Division Dhumakot |
RO MoRTH Dehradun |
12-Oct-19 |
12-Oct-19 |
MoRTH |
148702 |
Strengthening work from km. 101.00 to 107.00 on NH-123(New No. 507) in the State of Uttarakhand |
Under Implementation |
Awarded, not Appointed |
RO MoRTH Dehradun |
NH Division Barkot |
RO MoRTH Dehradun |
12-Oct-19 |
12-Oct-19 |
MoRTH |
124317 |
Construction of 2 lane with paved shoulder of Kund Bypass from Design Km 35.130 to Km 47.700 (existing Km 33.130 to Km 41.260) of NH-109 in the State of Uttarakhand |
Under Implementation |
Under Const. |
RO MoRTH Dehradun |
NH Division Rudraprayag |
RO MoRTH Dehradun |
12-Oct-19 |
12-Oct-19 |
MoRTH |
80689 |
Rehabilitation and up gradation to 2-lane with paved shoulder from existing km 172.900 to km 194.150 (Design chainage km 49.300 to km 70.300) on dharasu to yamunotri road of NH-134(old NH 94) in the state of uttarakhand under improvement of NH connectivity to chardham. |
Under Implementation |
Under Const. |
RO MoRTH Dehradun |
NH Division Barkot |
RO MoRTH Dehradun |
12-Oct-19 |
12-Oct-19 |
MoRTH |
80665 |
Construction of 4 nos bridges in km. 139 to 196 on NH-119 |
Under Implementation |
Under Const. |
RO MoRTH Dehradun |
NH Division Dhumakot |
RO MoRTH Dehradun |
12-Oct-19 |
12-Oct-19 |
MoRTH |
80597 |
Widening and Strengthening/ Reconstruction of Existing 2-Lane To 2 Lane with Paved Shoulder Configuration from existing km 338+100 (Design km 333.400) to km 368+000 (Design km 360.579) excluding existing km 349+800 to km. 355+495 (Kaliyasaur Bypass) of NH-58 In the State of Uttarakhand through an Engineering, Procurement and Construction (EPC) Contract |
Under Implementation |
Under Const. |
RO MoRTH Dehradun |
NH Division Srinagar |
RO MoRTH Dehradun |
12-Oct-19 |
12-Oct-19 |
MoRTH |
80592 |
Construction of 15 M span RCC motor bridge ate km. 143.090 on NH-707A |
Under Implementation |
Under Const. |
RO MoRTH Dehradun |
NH Division Doiwala |
RO MoRTH Dehradun |
12-Oct-19 |
12-Oct-19 |
MoRTH |
80591 |
Constrcution of 18 M span RCC motor bridge at km. 48.350 on NH-707A |
Under Implementation |
Under Const. |
RO MoRTH Dehradun |
NH Division Doiwala |
RO MoRTH Dehradun |
12-Oct-19 |
12-Oct-19 |
MoRTH |
80590 |
Strengthening from km. 52.350 to km. 61.750, km. 70.750 to 72.825 and km. 80.00 to 83.00 on NH-707A in the state of uttarakhand. |
Under Implementation |
Under Const. |
RO MoRTH Dehradun |
NH Division Doiwala |
RO MoRTH Dehradun |
12-Oct-19 |
12-Oct-19 |
MoRTH |
80585 |
Installation of crash barriers on various stretches of National Highways in the state of Uttarakhand |
Under Implementation |
Under Const. |
RO MoRTH Dehradun |
NH Division Doiwala |
RO MoRTH Dehradun |
12-Oct-19 |
12-Oct-19 |
MoRTH |
66982 |
Rehabilitation and upgradation to 2 lane with paved shoulder configuration from km 122.00 (Dharasu Bend) to km 147.230 (Silkyara Bend) of NH-94 in the state of Uttarakhand |
Under Implementation |
Under Const. |
RO MoRTH Dehradun |
NH Division Barkot |
RO MoRTH Dehradun |
12-Oct-19 |
12-Oct-19 |
MoRTH |
64900 |
Construction of 12.00 M span RCC motor bridge at km. 5.25 of NH-707A in the State of Uttarakhand |
Under Implementation |
Under Const. |
RO MoRTH Dehradun |
NH Division Doiwala |
RO MoRTH Dehradun |
12-Oct-19 |
12-Oct-19 |
MoRTH |
64897 |
Construction of 30.00 M span RCC motor bridge at km. 43.650 of NH-707A in the State of Uttarakhand |
Under Implementation |
Under Const. |
RO MoRTH Dehradun |
NH Division Doiwala |
RO MoRTH Dehradun |
12-Oct-19 |
12-Oct-19 |
MoRTH |
64893 |
Improvement /Widening to 2-lane with paved shoulder including major bridge & protection work of Paligaad market on Hill side and valley side from km. 196.00 to 197.00 on NH-94 (New No. 134) in UK |
Under Implementation |
Under Const. |
RO MoRTH Dehradun |
NH Division Barkot |
RO MoRTH Dehradun |
12-Oct-19 |
12-Oct-19 |
MoRTH |
62568 |
RECONSTRUCTION WITH GEOMETRIC IMPROVMENT OF EXISTING INTERMEDIATE LANE TO 2 LANE WITH PAVED SHOULDER CONFIGEURATION FROM KM. 28.600 TO 59.420 (DSIGN CHAINAGE 28.320 TO KM 58.603) of NH-94 IN THE STATE OF UTTARAKHAND ON EPC MODE UNDER IMPROVEMENT TO N |
Under Implementation |
Under Const. |
RO MoRTH Dehradun |
PIU-Dehradun, MoRTH |
RO MoRTH Dehradun |
12-Oct-19 |
12-Oct-19 |
MoRTH |
62564 |
Construction of 2-Lane ROB and its approaches in lieu of existing level Crossing (L.C.No. 39-B) at Km 158.525 on NH-74 in the state of Uttarakhand on EPC Mode |
Under Implementation |
Under Const. |
RO MoRTH Dehradun |
NH Division Haldwani |
RO MoRTH Dehradun |
12-Oct-19 |
12-Oct-19 |
MoRTH |
60146 |
Widening of existing single lane road to two lane with paved shoulder from km. 235.00 to 268.00 of NH-58 including 600 m marine drive viaduct portion near Byasi in Uttarakhand under EPC mode |
Under Implementation |
PCOD |
RO MoRTH Dehradun |
NH Division Srinagar |
RO MoRTH Dehradun |
12-Oct-19 |
12-Oct-19 |
MoRTH |
60145 |
Reconstruction with geometric improvement of existing 2L/IL to 2L with paved shoulder from km. 268.00 to 300.00 of NH-58 in Uttarakhand under EPC mode |
Under Implementation |
PCOD |
RO MoRTH Dehradun |
NH Division Srinagar |
RO MoRTH Dehradun |
12-Oct-19 |
12-Oct-19 |
MoRTH |
54164 |
Reconstruction with geometric improvement of existing intermediate lane to 2 lane with paved shoulder configuration from km 1.95 to km 28.600 (excluding the stretch from km 13.800 to km 18.550) of NH-94 in the state of Uttarakhand on EPC mode. |
Under Implementation |
Under Const. |
RO MoRTH Dehradun |
PIU-Dehradun, MoRTH |
RO MoRTH Dehradun |
12-Oct-19 |
12-Oct-19 |
MoRTH |
54162 |
Reconstruction with geometric improvement of existing 2 lane/intermediate lane to 2lane with paved shoulder configuration from km. 300 to 338 of NH-58 in the State of Uttarakhand under EPC mode |
Under Implementation |
Under Const. |
RO MoRTH Dehradun |
NH Division Srinagar |
RO MoRTH Dehradun |
12-Oct-19 |
12-Oct-19 |
MoRTH |
50289 |
Protection work of NH-119 (New No. 534) at KM- 149 HM (8-10) and KM- 150 HM (8-10) in the State of U |
Under Implementation |
Under Const. |
RO MoRTH Dehradun |
NH Division Dhumakot |
RO MoRTH Dehradun |
12-Oct-19 |
12-Oct-19 |
MoRTH |
50276 |
Widening and Strenthening of existing intermediate / 2-lane to 2-lane with paved shoulder configuration from km. 0.00 (Design km. 0.00) to km. 16.440 (Design km. 18.700) including existing 3.470 km of Rudraprayag Bypass of NH-109 in the State of UK |
Under Implementation |
Under Const. |
RO MoRTH Dehradun |
NH Division Rudraprayag |
RO MoRTH Dehradun |
12-Oct-19 |
12-Oct-19 |
MoRTH |
50268 |
Widening of existing 2 lane to 4 lane in km. 156.00 to 161.00 (I.S.B.T. to Ajabpur Railway Crossing) of NH-72 (New No-07) in UK |
Under Implementation |
Under Const. |
RO MoRTH Dehradun |
NH Division Doiwala |
RO MoRTH Dehradun |
12-Oct-19 |
12-Oct-19 |
MoRTH |
50262 |
Mitigation of Lambagarh Landslide at km. 504.309 onNH-58 in the State of Uttarakhand |
Under Implementation |
Under Const. |
RO MoRTH Dehradun |
NH Division Rudraprayag |
RO MoRTH Dehradun |
12-Oct-19 |
12-Oct-19 |
MoRTH |
139919 |
Washim(km 92.200) to Pangare(134.500) of NH-161 in Maharashtra |
Under Implementation |
Under Const. |
RO-Nagpur |
PIU-Washim |
PD-Washim |
5-Feb-20 |
10-Dec-19 |
NHAI |
139832 |
Hiran River to Sindoor River (Km.66.00 - Km.130.00) |
Under Implementation |
Under Const. |
RO-Bhopal |
PIU-Narsinghpur |
PD-Narsinghpur |
4-Feb-20 |
9-Oct-19 |
NHAI |
139348 |
Yedshi (Km.100.000) to Aurangabad (Km.290.200) |
Under Implementation |
PCOD |
RO-Nagpur |
PIU-Aurangabad |
PD-Aurangabad |
4-Feb-20 |
10-Dec-19 |
NHAI |
140365 |
Delhi/ Haryana Border to Rohtak section including Bahadurgarh and Rohtak by-passes |
Under Implementation |
PCOD |
RO-Chandigarh |
PIU-Rohtak |
PD-Rohtak |
3-Feb-20 |
6-Aug-19 |
NHAI |
139333 |
Tirupati - Tiruttani - Chennai Section of NH-205 in the State of Andhra Pradesh and Tamil Nadu |
Under Implementation |
PCOD |
RO-Chennai |
PIU-Chennai |
PD-Chennai |
7-Jan-20 |
11-Jan-20 |
NHAI |
139461 |
Chennai-Tada |
Under Implementation |
Under Const. |
RO-Chennai |
PIU-Chennai |
PD-Chennai |
7-Jan-20 |
11-Jan-20 |
NHAI |
139870 |
(i) Balance work of TPP Road - (ii) Improvement of MORR and IRR; (iii) Improvement of Ennore Express |
Under Implementation |
PCOD |
RO-Chennai |
PIU-Chennai |
PD-Chennai |
7-Jan-20 |
11-Jan-20 |
NHAI |
139388 |
Solan - Kaithlighat Section of NH-22 Now NH-5 from Km. 106.139 to Km.129.05 |
Under Implementation |
Under Const. |
RO-Shimla |
PIU-Shimla |
PD-Shimla |
6-Jan-20 |
7-Nov-19 |
NHAI |
139839 |
Shimla Bypass (Kaithlighat (Km 129.050) to Dhalli (Km 156.507) |
Under Implementation |
Under Const. |
RO-Shimla |
PIU-Shimla |
PD-Shimla |
6-Jan-20 |
7-Nov-19 |
NHAI |
139843 |
Parwanoo (Km 67.00) to Solan (Km 106.14) of NH-22 in Himachal Pradesh |
Under Implementation |
Under Const. |
RO-Shimla |
PIU-Shimla |
PD-Shimla |
6-Jan-20 |
7-Nov-19 |
NHAI |
139780 |
Maheshkunt -Saharsa-Purnea Pkg II |
Under Implementation |
Under Const. |
RO-Patna |
PIU-Begusarai |
PD-Begusarai |
4-Jan-20 |
16-Apr-19 |
NHAI |
139893 |
Myanmar Project (Yargi - Kalewa) |
Under Implementation |
Under Const. |
RO-Guwahati |
PIU-Myanmar |
PD-Myanmar |
8-Oct-18 |
26-Dec-19 |
NHAI |