Highway Constructed

*48,476 Km

FASTag Issued

52.59 Lakh

Online Driving Licences

Vehicle Registration (CFY)

Lakh

  Highway Construction Target v/s Achieved (Km. in CFY)

  Target Length Under Various Programmes (Km.)

  Focus Projects

  Highway Construction Progress (Km. in CFY)

  List of Defaulters, who did not certify data in PMIS

Project Id Project Name Current Stage Detailed Stage RO PIU User PD Certification Date RO Certification Date Organization
124094 Consultancy Services for Feasibility Study cum DPR, Survey and Preparation of Land Plan by adopting LiDAR or similar technology for Widening to two lane with Paved Shoulders Indi-Zalki-Chadachan-Shiradon – Maharahstra Border . Under Implementation Awarded, not Appointed RO MoRTH Bengaluru NH Division, Bijapur RO MoRTH Bengaluru 20-Feb-20 20-Feb-20 MoRTH
124092 Consultancy Services for Feasibility Study cum DPR, Survey and Preparation of Land Plan by adopting LiDAR or similar technology for Widening to two lane with Paved Shoulders Junction of NH-50 near Hungund-Aihole-Pattadakal-Badami-Ramdurg for an approximate length 85.00 km in the State of Karnataka.-857 Under Implementation Awarded, not Appointed RO MoRTH Bengaluru NH Division, Bijapur RO MoRTH Bengaluru 20-Feb-20 20-Feb-20 MoRTH
124089 Vijayapura-Yatnal Guddapur-Jath-Junction of NH-166 Near Nagaj (Vijayapura-Yatnal) about 30.00 kms & Providing by pass to Vijayapura City from NH-13 (Old) Solapur-Vijayapura Section Connecting this road about 17.00 Kms for length 47.00 km Under Implementation Awarded, not Appointed RO MoRTH Bengaluru NH Division, Bijapur RO MoRTH Bengaluru 20-Feb-20 20-Feb-20 MoRTH
50486 Chitradurga-Shimoga Under Implementation Under Const. RO MoRTH Bengaluru NH Division, PPP Cell, Shimoga RO MoRTH Bengaluru 20-Feb-20 20-Feb-20 MoRTH
50484 Madhugiri-Chikkaballapura- Mulbagal Section Km 343.800 to Km 400.330 Lot -I of NH-234 Under Implementation Under Const. RO MoRTH Bengaluru NH Division, PPP Cell, Chikkballapura RO MoRTH Bengaluru 20-Feb-20 20-Feb-20 MoRTH
50485 Rehabiliatation and Upgrading to 2 lanes/ 2 lanes with paved shoulders from Km.400.330 to Km.483.151 -Lot-II of NH-234 Under Implementation Under Const. RO MoRTH Bengaluru NH Division, PPP Cell, Chikkballapura RO MoRTH Bengaluru 20-Feb-20 20-Feb-20 MoRTH
50437 Bijapur-Hubli section Km 153.00 to Km 193.350 Under Implementation Under Const. RO MoRTH Bengaluru NH Division, Hubli RO MoRTH Bengaluru 20-Feb-20 20-Feb-20 MoRTH
146190 Widening of CC pavement in km 0/035 - 1/230 including widening and strengthening of existing bituminous surface in km 0/0 - 0/035, reconstruction of storm water drain at km 0/0-1/400 & construction of crash barrier type center median and paved shoulders of NH45A in the state of Tamil Nadu Under Implementation Under Const. RO MoRTH Chennai NHDivisionVillupuram PD-NH Division Villupuram 16-Feb-20 26-Dec-19 MoRTH
137819 Widening of Four Lane, Construction of Storm water drain, centre median and providing paver block from Km 2/4-7/4 of NH45A (Villupuram - Pondy - Nagapattinam Road) Under Implementation Under Const. RO MoRTH Chennai NHDivisionVillupuram PD-NH Division Villupuram 16-Feb-20 26-Dec-19 MoRTH
146192 Widening of CC Pavement to km.1/800- 2/400 including widening and strengthening of existing bituminous surface from km.1/230-1/400 & 1/760-1/800, strengthening in km.1/400-1/760, Reconstruction of storm water drain at Km 1/800-2/400, constrution of crash barrier type center median and paved shoulders of NH45A (Villupuram-Pondicherry-Nagapattinam road) in the state of Tamil Nadu Under Implementation Under Const. RO MoRTH Chennai NHDivisionVillupuram PD-NH Division Villupuram 16-Feb-20 26-Dec-19 MoRTH
55560 Strengthening with paved shoulder from km 858/000 to 862/000, 868/000 to 875/000, 876/000 to 879/000, from Km 888/0 to 892/0, Km 907/0 to 912/348 and Km 912/780 to 915/0 including paved shoulder from Km 862/000 to 868/000 and 875/000 to 876/000 Under Implementation Under Const. RO MoRTH Guwahati Construction Division Abhayapuri Construction Division Abhayapuri 10-Feb-20 28-Nov-19 MoRTH
143623 Widening and improvement of Kajri Patan Manatu Road from km 16.40 to 34.40 Under Implementation Under Const. RO MoRTH Ranchi Road Division, Daltonganj RO MoRTH Ranchi 10-Feb-20 10-Feb-20 MoRTH
143486 Construction of Box cell culverts at km 140/200 km, 147/400 km & 155/100 km of NH - 23 Under Implementation Under Const. RO MoRTH Ranchi NH Division Gumla RO MoRTH Ranchi 10-Feb-20 10-Feb-20 MoRTH
143319 Strengthening of road from km 0.00 to km 41.80 of NH - 133A Under Implementation Under Const. RO MoRTH Ranchi NH Division Deoghar RO MoRTH Ranchi 10-Feb-20 10-Feb-20 MoRTH
143305 Strengthening of road from km 73.00 to 119.175 of NH - 100 Under Implementation Under Const. RO MoRTH Ranchi NH Division Hazaribagh RO MoRTH Ranchi 10-Feb-20 10-Feb-20 MoRTH
143310 Construction of Box cell culverts in km 49.00 to 62.00 of NH - 100 Under Implementation Under Const. RO MoRTH Ranchi NH Division Hazaribagh RO MoRTH Ranchi 10-Feb-20 10-Feb-20 MoRTH
143267 Strengthening of road from km. 44.00 to km. 71.00 of NH - 143A Under Implementation Under Const. RO MoRTH Ranchi NH Division Gumla RO MoRTH Ranchi 10-Feb-20 10-Feb-20 MoRTH
143271 Strengthening of road from km. 10.00 to km. 23.215 of NH-78 Under Implementation Under Const. RO MoRTH Ranchi NH Division Gumla RO MoRTH Ranchi 10-Feb-20 10-Feb-20 MoRTH
143302 Strengthening work of Hatgamharia-Jaintgarah road from km. 176.000 to 202.900 of NH - 75Ext. Under Implementation Under Const. RO MoRTH Ranchi NH Division Chaibaja RO MoRTH Ranchi 10-Feb-20 10-Feb-20 MoRTH
123421 Construction of new bridge over Durangi Nala in 108th km of NH-75 Under Implementation Under Const. RO MoRTH Ranchi NH Division Ranchi RO MoRTH Ranchi 10-Feb-20 10-Feb-20 MoRTH
122536 Strengthening work in Km 12.325 to 62.760 of NH-114A Under Implementation Under Const. RO MoRTH Ranchi NH Division Deoghar RO MoRTH Ranchi 10-Feb-20 10-Feb-20 MoRTH
122535 Strengthening work in Km 29.50 to 48.05 & Km 52.03 to 57.00 of NH-98 Under Implementation Under Const. RO MoRTH Ranchi NH Division Medininagar RO MoRTH Ranchi 10-Feb-20 10-Feb-20 MoRTH
68314 Widening to 2-lane with paved shoulder & improvement from Km 41.00 to 54.00 of NH-220 in the state of Jharkhand. Under Implementation Under Const. RO MoRTH Ranchi NH Division Chaibaja RO MoRTH Ranchi 10-Feb-20 10-Feb-20 MoRTH
64844 Widening to two lane with paved shoulder & Geometric Improvements from Km 184 to 216 on NH-114A Under Implementation Under Const. RO MoRTH Ranchi NH Division Dhanbad RO MoRTH Ranchi 10-Feb-20 10-Feb-20 MoRTH
59042 Widening and Strengthening work in Km 141 to 184 of NH-114A Under Implementation Under Const. RO MoRTH Ranchi NH Division Deoghar RO MoRTH Ranchi 10-Feb-20 10-Feb-20 MoRTH
58749 Construction of HL bridge over Local Nala in km 118 of NH-343 Under Implementation Under Const. RO MoRTH Ranchi NH Division Medininagar RO MoRTH Ranchi 10-Feb-20 10-Feb-20 MoRTH
58748 Construction of HL bridge over Local Nala in km 113 of NH-343 Under Implementation Under Const. RO MoRTH Ranchi NH Division Medininagar RO MoRTH Ranchi 10-Feb-20 10-Feb-20 MoRTH
50837 Widening and Strengthening work in Km 0 to 12.80 of NH-333A Under Implementation PCOD RO MoRTH Ranchi NH Division Deoghar RO MoRTH Ranchi 10-Feb-20 10-Feb-20 MoRTH
50831 bridge in km 102.60, 107.185, 107.368 & 115.875 of NH-99 Under Implementation Under Const. RO MoRTH Ranchi NH Division Ranchi RO MoRTH Ranchi 10-Feb-20 10-Feb-20 MoRTH
50815 Remaining work of Widening to intermediate lane and improvement of Sisai Basia Road from Km 0.0 to 37.775 Under Implementation Under Const. RO MoRTH Ranchi Road Division Gumla RO MoRTH Ranchi 10-Feb-20 10-Feb-20 MoRTH
50817 Widening and Strengthening of 2 Lane & Improvement of Lohardaga Kisko More to Richuguta Road from Km 0.00 to 31.50 (balance work) Under Implementation Under Const. RO MoRTH Ranchi Road Division, Lohardaga RO MoRTH Ranchi 10-Feb-20 10-Feb-20 MoRTH
50812 bridge in km 95.37, 98.19 and 100.87 of NH-75 Under Implementation Under Const. RO MoRTH Ranchi NH Division Ranchi RO MoRTH Ranchi 10-Feb-20 10-Feb-20 MoRTH
50801 Widening and Strengthening of Road work and reconstruction of culverts in km 31 to 61 (Chainage km 30 to 60.50) of NH-99 Under Implementation Under Const. RO MoRTH Ranchi NH Division Hazaribagh RO MoRTH Ranchi 10-Feb-20 10-Feb-20 MoRTH
50797 Construction of bridge in km 75/1, 76/1, 78/4 & 78/8 of NH-99 (Part-4) Under Implementation Under Const. RO MoRTH Ranchi NH Division Hazaribagh RO MoRTH Ranchi 10-Feb-20 10-Feb-20 MoRTH
50793 bridge over Katabil Nala Under Implementation Under Const. RO MoRTH Ranchi NH Division Ranchi RO MoRTH Ranchi 10-Feb-20 10-Feb-20 MoRTH
50796 Construction of bridge in km 37/1, 39/1 of NH-99 (Part-2) Under Implementation Under Const. RO MoRTH Ranchi NH Division Hazaribagh RO MoRTH Ranchi 10-Feb-20 10-Feb-20 MoRTH
50784 Construction of bridges in km 250.300, 252 & 256 of NH-75 Under Implementation Under Const. RO MoRTH Ranchi NH Division Medininagar RO MoRTH Ranchi 10-Feb-20 10-Feb-20 MoRTH
102069 Construction of Signature Bridge between Dwarka & bey Dwarka and its approaches in the State of Gujarat on EPC Mode [NH-51/Gujarat(02) 17-20-S & R (B)] Under Implementation Under Const. RO MoRTH Gandhinagar NH Division Rajkot NH Division Rajkot 10-Feb-20 25-Oct-19 MoRTH
148718 Construction of 6.00 Mtr Span Double lane Class A loading RCC Culvert in km 175 (HM-2-4) of NH-309A in the state of Uttarakhand under NH(O) Annual plan 2018-19 Under Implementation Awarded, not Appointed RO MoRTH Dehradun NH Division Ranikhet NH Division Ranikhet 10-Feb-20 12-Oct-19 MoRTH
144101 "I.R.Q.P Work from km 23.20 to km 25.70 of N.H.-34 under N.H Division No.V, P.W.(Roads) Directorate in the District of North 24 Parganas, West Bengal during the 2018-19 on SBD mode. (Job No.034-WB-2016-17/431)" Under Implementation Under Const. RO MoRTH Kolkata NH Division-V NH Division-V 6-Feb-20 17-Oct-19 MoRTH
58469 Construction of Twins 2-lane ROB and its approaches in replacement of existing level crossing Gate No. -KA-34 (Rly km 160/25-160/27) between Mindapore & Bankura stations in Kubai at km 154.617 of NH-60. Under Implementation Under Const. RO MoRTH Kolkata NH Division-II NH Division-II 5-Feb-20 17-Oct-19 MoRTH
62565 Reconstruction With geometric improvement of existing two lane to 2- Lane with paved shoulders configuration from existing Km. 126.73 to 135.075 & km.143.75 to 163.00(Pithoragarh-Tanakpur Project road)of NH-125 in the state of UttaraKhand on EPC mode Under Implementation Under Const. RO MoRTH Dehradun NH Division Lohaghat NH Division Lohaghat 4-Feb-20 12-Oct-19 MoRTH
62567 Reconstruction with geometric improvement of single/intermediate Lane to 2- Lane with paved shoulder configuration from existing Km. 92.880 to Km 121.550 (Design chainage 91.550 to120.455) of NH-125 in the state of UttaraKhand on EPC mode Under Implementation Under Const. RO MoRTH Dehradun NH Division Lohaghat NH Division Lohaghat 4-Feb-20 12-Oct-19 MoRTH
60147 Reconstruction of existing 2 L/IL to 2L with paved shoulder from existing km 52.200 to 92.880 of NH- Under Implementation Under Const. RO MoRTH Dehradun NH Division Lohaghat NH Division Lohaghat 4-Feb-20 12-Oct-19 MoRTH
62566 Reconstruction With geometric improvement of single Lane to 2- Lane with paved shoulder configuration from existing Km. 163.00 to Km 194.800(Design chainage 160.88 to 192.320) of NH-125 in the state of UttaraKhand on EPC mode Under Implementation Under Const. RO MoRTH Dehradun NH Division Lohaghat NH Division Lohaghat 4-Feb-20 12-Oct-19 MoRTH
149422 Stage Strengthening of the existing pavement from 0.00 Kmp to 49.00 kmp of NH- 2B under National Highway Division No:-III of N.H.C.-II during the year 2019-20 in the district of Purba Bardhaman & Birbhum ,West Bengal in EPC Mode. (Job No. 26-WB-2019-20/441) Under Implementation Awarded, not Appointed RO MoRTH Kolkata NH Division-III NH Division-III 3-Feb-20 MoRTH
149421 Stage Strengthening from 260 kmp to 266 kmp and 271 kmp to 275 kmp (except 273.05 km to 273.85 km) of NH-60 under N.H Division No.III, P.W.(Roads) Directorate in the District of Bankura & Paschim Bardhaman, West Bengal on EPC mode. (Job No. 60-WB-2019-20/440) Under Implementation Under Const. RO MoRTH Kolkata NH Division-III NH Division-III 3-Feb-20 MoRTH
122754 Tolakurwa to Bishnupur ( via Chakai) Under Implementation Under Const. RO MoRTH Patna NH Division Lakhisarai NH Division Lakhisarai 3-Feb-20 11-Dec-19 MoRTH
62910 HL RCC minor bridge in km 24 Under Implementation Under Const. RO MoRTH Patna NH Division Lakhisarai NH Division Lakhisarai 3-Feb-20 11-Dec-19 MoRTH
124078 Construction ofProposed 4-Lane ROBand its approaches in lieu of existing level crossing No. 95/SPL @ Km 272.600( Railway Chainage 93/17-19) on NH 205 in the State of A.P. Job No. NH-205 /AP(36)/17-S&R(B)018 dt 07-07-2017 Under Implementation Under Const. RO MoRTH Vijayawada NH Division KADAPA NH Division KADAPA 3-Feb-20 13-Dec-19 MoRTH
54163 Widening and strengthening of existing single /2lane to 2 lane with earthen shoulder configuration from km. 57.975 to km. 68.600 (Fata to Sitapur) on NH-109(New No. 107) in the State of Uttarakhand under EPC Mode Under Implementation Under Const. RO MoRTH Dehradun NH Division Rudraprayag NH Division Rudraprayag 7-Jan-20 12-Oct-19 MoRTH
50274 Construction of 2-lane with paved shoulders configuration & strengthening of NH-58 from km 350.00 to km. 355.00 (Kaliyasaur re-alignment) in the State of Uttarakhand on EPC Mode Under Implementation Under Const. RO MoRTH Dehradun NH Division Rudraprayag NH Division Rudraprayag 6-Jan-20 12-Oct-19 MoRTH
55566 Strengthening with paved shoulders from Km 138/00 to 157/0 and Km 171/0 to 177/0 (Total length= 25.00 km.) under Nagaon NH Division (Job No. 052(New-15)/AS/2016-17/164 Under Implementation Under Const. RO MoRTH Guwahati NH Division Nagaon NH Division Nagaon 6-Jan-20 28-Nov-19 MoRTH
62130 Construction & Widening (Including Augustmuni Bypass Ch-16.545 to Ch - 19.890) to 2L/PS from Km 16.545-Km 33.130 & 45.980 -57.975 (Augustmuni to Kund & Guptkashi to Sitapur) on NH 109 in UK Under Implementation Under Const. RO MoRTH Dehradun NH Division Rudraprayag NH Division Rudraprayag 6-Jan-20 12-Oct-19 MoRTH
50701 Strengthening with paved shoulder from KM. 305/0 to 316/0 of NH-52(Total length=11.00 Km.) including providing retaining walls breast walls, culverts and drains in selected stretches under Nagaon NH Division in the state of Assam on E.P.C mode (Job No.052/AS/2014-15/124) Under Implementation Under Const. RO MoRTH Guwahati NH Division Nagaon NH Division Nagaon 6-Jan-20 28-Nov-19 MoRTH
124192 Strengthening with construction of paved shoulders from km 135/000 to km 138/000, km157/000 to 171/000 and km 177/000 to km 182/000 (Total Length = 22.00 km) of NH-52 (New NH-15) FOR THE YEAR 2017-18 UNDER Nagaon NH Division in the State of Assam. (Job No. 052(New NH-15)/AS/2017-18/180) Under Implementation Under Const. RO MoRTH Guwahati NH Division Nagaon NH Division Nagaon 6-Jan-20 28-Nov-19 MoRTH
143514 Construction of 2 lane NH with paved shoulders between Ch.396.4215 km and Ch.397.9885 km of NH-52(New NH-15) ,bituminous layers between Ch.407.428 km and Ch.408.030 km,Ch.419.99km and Ch. 440.000km of NH-52(New NH-15)for 10.00m width and between Ch. 436.760 km and Ch .436.915 km for 5.00 m width of NH-52 (New NH-15) and rehabilitation of bridge No. 308/1 opver river Kumatia including construction of guide bunds,river training work etc in Assam . SARDP-NE NH-15/AS/PWD/2016-17/289 Under Implementation Under Const. RO MoRTH Guwahati NH Division Nagaon NH Division Nagaon 4-Jan-20 28-Nov-19 MoRTH
68031 Rehabilitation and upgradation of Dornala T junction to Penchalakona Km 361/327 to 425/4 of Nh-565 in the state of Andhra Pradesh. Under Implementation Under Const. RO MoRTH Vijayawada NH Division KADAPA NH Division KADAPA 3-Jan-20 13-Dec-19 MoRTH
60530 Rehabilitation and up-gradation of NH-340 from km 0+000 to km 60+380 (Design Ch. 0/000 to 60/025) (Rayachoty to Angallu section) to two lane with paved shoulders in the State of Andhra Pradesh under Corridor Approach through Engineering, Procurement & Con Under Implementation Under Const. RO MoRTH Vijayawada NH Division KADAPA NH Division KADAPA 3-Jan-20 13-Dec-19 MoRTH
137317 Construction of 4-Lane ROBand its approaches in lien of existing level crossing No. 102/3E @ Km 281.200 of NH 205 in the State of A.P. Job No. NH-205 /AP(8)/15-16-010-S&R(B) dt 31-03-2016 Under Implementation Under Const. RO MoRTH Vijayawada NH Division KADAPA NH Division KADAPA 3-Jan-20 13-Dec-19 MoRTH
144084 Construction of ROB in km 24 (LC no. 77A) of NH 327A Under Implementation Awarded, not Appointed RO MoRTH Patna NH Division Madhepura NH Division Madhepura 3-Jan-20 11-Dec-19 MoRTH
144081 Construction of ROB in km 194 (LC no. 53B/T-2) of NH 327E Under Implementation Awarded, not Appointed RO MoRTH Patna NH Division Madhepura NH Division Madhepura 3-Jan-20 11-Dec-19 MoRTH
52320 Widening and Strengthening of existing carriageway for 4-laning of NH-34 for the stretch from Km. 25.700 to Km. 31.00 Under Implementation Under Const. RO MoRTH Kolkata NH Division-V NH Division-V 2-Jan-20 17-Oct-19 MoRTH
80176 Reconstruction of Bridge across river Pravadayanar @Ch 184/000 in NH45A in Karaikal district in the Unioun territory of Pondicherry Under Implementation Under Const. RO MoRTH Chennai PWD, Karaikal RO MoRTH Chennai 26-Dec-19 26-Dec-19 MoRTH
54027 Villupuram-Puducherry Under Implementation Under Const. RO MoRTH Chennai PWD, Puducherry RO MoRTH Chennai 26-Dec-19 26-Dec-19 MoRTH
148635 Construction of 4 Lane ROB and Subway in lien of level crossing no. 17 @ km 108/1-2 between Jamalamagudu & Proddator Station on Nandyal-Yerraguntla section at km 563/200 of NH-67 EPC mode in the state of A.P. Job No. NH-67-AP-17-18-672 dt 28-03-2018 Under Implementation Under Const. RO MoRTH Vijayawada NH Division KADAPA RO MoRTH Vijayawada 13-Dec-19 13-Dec-19 MoRTH
144969 Rehabilitiation and upgradation of Chittoor - Kurnool Road NH-18 (New NH-40) from 2 lane to 4 Lane from Km 4/14 to 18/34 (excluding 2.94 Km ROB Portion) from Murkumbattu Junction to Rangampet cross in the State of Andhra Pradesh through EPC mode Under Implementation Under Const. RO MoRTH Vijayawada NH Division Chittor RO MoRTH Vijayawada 13-Dec-19 13-Dec-19 MoRTH
144967 Improvement to NH-544D(Anantapur-Guntur Road) from Km 414 to 417 (i.d.) from Chuttugunta junction to NH-16 junction) including widening in Guntur Municipal limits in the state of Andhra Pradesh on EPC mode. Under Implementation Under Const. RO MoRTH Vijayawada NH Division VIJAYAWADA RO MoRTH Vijayawada 13-Dec-19 13-Dec-19 MoRTH
141388 Construction of proposed 4- lane RoB at Railway Chainage km 44/679 between Puthalapattu -RVS Nagar Station of kathipudi- pakala Section @km 12/4 on NH 18 in the state of Andhra Pradesh on EPC Mode [job.no. 18-AP-2018-19-676 dt:16.01.19 Under Implementation Under Const. RO MoRTH Vijayawada NH Division Chittor RO MoRTH Vijayawada 13-Dec-19 13-Dec-19 MoRTH
141387 Strenghtening in selected stretches (25.6) from km 0/0 to 4/0, km 16/0 to 22/2, km 23/2 to 24/4, km 30/4 to 32/2, km 33/0 to 39/0, km 53/0 to 54/6, km 55/9 to 56/5, km 58/0 to 59/1 , km 60/0 to 60/6 & km 61/4 to 63/9 of Renigunta to kadapa Road NH-716 in the state of A.P. [Job.no. 716-AP-2018-19-675 dt: 09.01.19 Under Implementation Under Const. RO MoRTH Vijayawada NH Division KADAPA RO MoRTH Vijayawada 13-Dec-19 13-Dec-19 MoRTH
141386 Improvement the selected stretches (21.20 km) to the road from km. 0/0 to 40/2 of puttur-Uthukottai road NH-716A in the state of Andhra Pradesh on EPC mode [job.no. 716A-AP-2018-19-674 dt:04.12.18] Under Implementation Under Const. RO MoRTH Vijayawada NH Division KADAPA RO MoRTH Vijayawada 13-Dec-19 13-Dec-19 MoRTH
139241 Construction of Proposed 4-Lane ROB and its approaches in lien of existing level crossing No. 67 @ Km 133.20( Railway Chainage 109/3-4) on NH 205 in the State of A.P. Job No. NH-205 /AP(38)/16-17-013-S&R(B) dt 24-03-2017 Under Implementation Under Const. RO MoRTH Vijayawada NH Division Chittor RO MoRTH Vijayawada 13-Dec-19 13-Dec-19 MoRTH
139239 Construction of Proposed 4-Lane ROB and its approaches in lien of existing level crossing No. 75 @ Km 145.200( Railway Chainage 121/470) on NH 205 in the State of A.P. Job No. NH-205 /AP(4)/17-S&R(B)020 dt 07-07-2017 Under Implementation Under Const. RO MoRTH Vijayawada NH Division Chittor RO MoRTH Vijayawada 13-Dec-19 13-Dec-19 MoRTH
139238 Construction ofProposed 4-Lane ROBand its approaches in lien of existing level crossing No. 45 C @ Km 93.40( Railway Chainage 70/903) on NH 205 in the State of A.P. Job No. NH-205 /AP(3)/17-S&R(B)019 dt 07-07-2017 Under Implementation Under Const. RO MoRTH Vijayawada NH Division ANANTAPUR RO MoRTH Vijayawada 13-Dec-19 13-Dec-19 MoRTH
139237 Construction ofProposed 4-Lane ROBand its approaches in lien of existing level crossing No. 48E/C @ Km 96.80( Railway Chainage 74.431) on NH 205 in the State of A.P. Job No. NH-205 /AP(39)/16-17-012-S&R(B) dt 22-03-2017 Under Implementation Under Const. RO MoRTH Vijayawada NH Division ANANTAPUR RO MoRTH Vijayawada 13-Dec-19 13-Dec-19 MoRTH
137320 Construction ofProposed 4-Lane ROBand its approaches in lien of existing level crossing No. 30/E @ Km 64.800( Railway Chainage 42.858) on NH 205 in the State of A.P. Job No. NH-205 /AP(1)/16-17-016-S&R(B) dt 31-03-2017 Under Implementation Under Const. RO MoRTH Vijayawada NH Division ANANTAPUR RO MoRTH Vijayawada 13-Dec-19 13-Dec-19 MoRTH
137315 Construction of 4-Lane ROB and its approaches in lien of existing level crossing No.124E/SPL 3@ Km 1.800( New Chainage km 77.805 on NH 205 in the State of A.P. Job No. NH-205 /AP(2)/15-16-007-S&R(B) dt 14-03-2016 Under Implementation Under Const. RO MoRTH Vijayawada NH Division ANANTAPUR RO MoRTH Vijayawada 13-Dec-19 13-Dec-19 MoRTH
124086 Construction of 2-Lane ROB and its approaches in lien of level crossing No.414 @ Km 33.100 (Railway chainage 730/11-13) on NH-326A on EPC mode in the State of A.P. Job No. NH-326A-AP17-18 -671 dt 28-03-2018. Under Implementation Under Const. RO MoRTH Vijayawada NH Division KAKINADA RO MoRTH Vijayawada 13-Dec-19 13-Dec-19 MoRTH
124085 Construction of 2-Lane ROB and its approaches in lien of level crossing No. 31 @ Km 2.100 (Railway chainage 33/900-1000) on NH-326A on EPC mode in the State of A.P.Job No. NH-326 A -AP-17-18 -670 dt 28-03-2018. Under Implementation Under Const. RO MoRTH Vijayawada NH Division KAKINADA RO MoRTH Vijayawada 13-Dec-19 13-Dec-19 MoRTH
124082 Construction of 2-Lane ROB and subway in lien of level crossing No. 88 at Railway km 136/5-6 between Kurbalakota & Madanapalli Section on Dharmavaram-Pakala Section at km 56/100 of NH-340 on EPC mode in the State of A.P. Job No. NH-340 -AP17-18 -669 dt 28-03-2018. Under Implementation Awarded, not Appointed RO MoRTH Vijayawada NH Division KADAPA RO MoRTH Vijayawada 13-Dec-19 13-Dec-19 MoRTH
123729 Rehabilitation and upgradation of New NH 544DD from design Chainage Km. 56/000 to 102/20 of Kalyandrg - Molakalmuru Section Under Implementation Under Const. RO MoRTH Vijayawada NH Division ANANTAPUR RO MoRTH Vijayawada 13-Dec-19 13-Dec-19 MoRTH
91705 Rehabilitation and up-gradation of NH-42 from 76/000 to Km.102/130 (Design Ch. 76/000 to 99.971 excluding Km 77.300 to 78.350) (Rapthadu to Bathalapalli section) to four lane in the State of Andhra Pradesh through EPC Under Implementation Under Const. RO MoRTH Vijayawada NH Division ANANTAPUR RO MoRTH Vijayawada 13-Dec-19 13-Dec-19 MoRTH
91702 Rehabilitation and upgradation of NH 326A from km 0/0 to 41/979 (excluding km 2/255 to 3/372 and km 36/820 to 38/275) (Odisha border to Narasamapeta) to two lane with paved Shoulders in the State of Andhra Pradesh under NH(O) on EPC Mode Under Implementation Under Const. RO MoRTH Vijayawada NH Division KAKINADA RO MoRTH Vijayawada 13-Dec-19 13-Dec-19 MoRTH
67828 Rehabilitation and up-gradation of NH-544E from Km 0/00 to Km 56/803 (Design Ch. 0/00 to 56/803) (Kodikonda Junction to Madakasira section) to two lane with paved shoulder in the State of Andhra Pradesh under NH(O) on EPC mode Under Implementation Under Const. RO MoRTH Vijayawada NH Division ANANTAPUR RO MoRTH Vijayawada 13-Dec-19 13-Dec-19 MoRTH
64836 Rehabilitation and upgradation of Repalle to Eeppurpalem section from Km 129/927 to Km 195/000 of NH-214A (New NH-216) to two lane with paved shoulder under NHDP-IV on EPC basis Under Implementation Under Const. RO MoRTH Vijayawada PIU,MoRT&H, Machilipatnam RO MoRTH Vijayawada 13-Dec-19 13-Dec-19 MoRTH
64835 Rehabilitation and Up-gradation of Pasarlapudi to Dhindi section from Km 105/170 to Km 126/510 of NH -214 (New NH -216) to two lane with paved shoulder in the state of Andhra Pradesh under NHDP-IV Under Implementation Under Const. RO MoRTH Vijayawada PIU,MoRT&H, Machilipatnam RO MoRTH Vijayawada 13-Dec-19 13-Dec-19 MoRTH
64834 Rehabilittion and upgradation of Machilipatnam to Avanigadda section from km 84/550 - 124/200 of NH 214A (new NH 216) to two lane with paved shoulder in the State of AP under NHDPIV through EPC basis Under Implementation Under Const. RO MoRTH Vijayawada PIU,MoRT&H, Machilipatnam RO MoRTH Vijayawada 13-Dec-19 13-Dec-19 MoRTH
64831 Rehabilitation and Up-gradation of Thimmapuram to Gurajanapalli section from Km 26/150 to Km 41/161 of NH - 214 ( New NH - 216) to two lane with paved shoulder in the state of Andhra Pradesh under NHDP-IV Under Implementation Under Const. RO MoRTH Vijayawada PIU,MoRT&H, Machilipatnam RO MoRTH Vijayawada 13-Dec-19 13-Dec-19 MoRTH
60529 Rehabilitation and up-gradation of NH-75(Old NH-234) from Km 506/100 to Km 508/700 and Km 518/700 to Km 534/350 (Design Ch. Km 506/100 to 508/650 and 518/700 to 534/100) Mangalore to Thiruvannamalai Road to two lane with paved shoulders in the State of Andhra Pradesh on EPC mode Under Implementation Under Const. RO MoRTH Vijayawada NH Division Chittor RO MoRTH Vijayawada 13-Dec-19 13-Dec-19 MoRTH
60528 Rehabilitation and upgradation of NH-67 from Km 424/650 to Km 487/693( Gooty-Tadipatri-District Border section) to two lane with paved shoulders in the State of Andhra Pradesh under Corridor Approach through EPC Basis Contract Under Implementation Under Const. RO MoRTH Vijayawada NH Division ANANTAPUR RO MoRTH Vijayawada 13-Dec-19 13-Dec-19 MoRTH
60527 Rehabilitation and up-gradation of NH-167 from Km 14/900 to Km70/000 (Design Ch. 14/900 to 69/700) (Chintakunta to Adoni section) to two lane with paved shoulders in the State of Andhra Pradesh under Corridor Approach through Engineering, Procurement & Co Under Implementation Under Const. RO MoRTH Vijayawada NH Division KURNOOL RO MoRTH Vijayawada 13-Dec-19 13-Dec-19 MoRTH
60247 Rehabilitation and up-gradation of NH-42 from km 244/930 to km 299/775 (Madanapalli-Punganuru-Palamaneru Section) to two lane with paved shoulder in the state of Andhra Pradesh under Corridor Scheme on EPC Mode Under Implementation Under Const. RO MoRTH Vijayawada NH Division Chittor RO MoRTH Vijayawada 13-Dec-19 13-Dec-19 MoRTH
52029 Rehabilitation and upgradation of Gurajanapalli village - Polekuru village section (from km.41/161 to 59/800) and Komaragigi-pasarlapudi section (km 70/400 to 105/170) of NH-214 (new NH-216) to two lane with paved shoulder in the state of Andhra Prad Under Implementation Under Const. RO MoRTH Vijayawada PIU,MoRT&H, Machilipatnam RO MoRTH Vijayawada 13-Dec-19 13-Dec-19 MoRTH
52028 Rehabilitation and up-gradation of Karnataka/Andhra Border to Gooty section from Km.368/920 to Km. 424/225 of NH-67 to four lane with paved shoulder in the state of Andhra Pradesh under NHDP-IV on EPC basis Under Implementation Under Const. RO MoRTH Vijayawada NH Division ANANTAPUR RO MoRTH Vijayawada 13-Dec-19 13-Dec-19 MoRTH
52025 Rehabilitation and Up-gradation of Dhindi - Digamarru section from Km 126/510 to Km 135/740 of NH -214(New NH -216) and digamarru -Losari section from Km 0/000 tp Km 34/230 of NH-214 A(New Nh-216) to two lane with paved shoulder in the state of AP-NH Under Implementation Under Const. RO MoRTH Vijayawada PIU,MoRT&H, Machilipatnam RO MoRTH Vijayawada 13-Dec-19 13-Dec-19 MoRTH
52024 4 laning of 5.122 km of NH9(New NH69) from Km 269/900 (Des.Ch.0/0) to km275/622(Des.Ch.5/122)i.e.connecting of NH9 (1.4 km) with NH5 (3.6 km) including 6 lane Elevated fly over from Bhavanipuram to Kanakadurgamma Varadhi in Vijayawada Under Implementation Under Const. RO MoRTH Vijayawada NH Division VIJAYAWADA RO MoRTH Vijayawada 13-Dec-19 13-Dec-19 MoRTH
52023 Rehabilitation & Upgradation of NH214(New NH-216) from Km 34/230 to Km 84/550 (Losari to Machavaram Section) to two lane with paved shoulder in the state of Andhrapradesh under NHDP-IV through Engineering, Procurement& Construction (EPC) mode. Under Implementation Under Const. RO MoRTH Vijayawada PIU,MoRT&H, Machilipatnam RO MoRTH Vijayawada 13-Dec-19 13-Dec-19 MoRTH
52017 Construction of 4-lane ROB in lieu of LC No.122 at km 160/800 Chittor - Kurnool road NH-18 (New NH-40) Under Implementation Under Const. RO MoRTH Vijayawada NH Division KADAPA RO MoRTH Vijayawada 13-Dec-19 13-Dec-19 MoRTH
52015 Rehabilitation and Upgradation of NH-219 from km.58/600 to 140/680 (Palamaneru to Krishnagiri Border Section) to two lane with paved shoulders in the State of AP under Corridor Aproach on EPC mode Under Implementation Under Const. RO MoRTH Vijayawada NH Division Chittor RO MoRTH Vijayawada 13-Dec-19 13-Dec-19 MoRTH
52004 Construction of proposed 4-lane ROB and its approaches in lieu of existing Level Crossing No.23/SPL class at Km 3.6 on NH-18 between Chittoor & RVS Nagar railway stations on Chittoor - Pakala Railway section in the state of Andhra Pradesh on EPC Under Implementation Under Const. RO MoRTH Vijayawada NH Division Chittor RO MoRTH Vijayawada 13-Dec-19 13-Dec-19 MoRTH
50614 Construction of ROB on NH-81 at Km 48 Under Implementation Under Const. RO MoRTH Patna NH Division Purnea RO MoRTH Patna 11-Dec-19 11-Dec-19 MoRTH
50600 Construction of ROB on NH-81 at Km 31 Under Implementation Under Const. RO MoRTH Patna NH Division Purnea RO MoRTH Patna 11-Dec-19 11-Dec-19 MoRTH
123282 Widening to four lane and Strenthening in selected strech of Ahmedabad-Dandi (Package 2, 6km ) Route from KM 71/200 to KM 77/600 of N.H. 64 i.e. Nadiad DDIT - Uttarsanda-Bhumel in the state of Gujarat. NH No.: 64 (Old NH-228) Under Implementation Under Const. RO MoRTH Gandhinagar NH Division Varodara NH Division Varodara 9-Dec-19 25-Oct-19 MoRTH
58460 Improvement of road safety through foothpaths, drains , improvements of junctions, road signs/ marking etc . in Anand city limits from km 85/600 to 90/300 NH-64 (Old NH-228) in the state of Gujarat Under Implementation Under Const. RO MoRTH Gandhinagar NH Division Varodara NH Division Varodara 9-Dec-19 25-Oct-19 MoRTH
144355 Strengthening of 2-lane with paved shoulder of NH-54 from 12th km to 40th km under Annual plan for the year 2018-19 on EPC mode PWD, NH Division, Silchar in the State of Assam. (Job No. 054/AS/2018-19/184) Under Implementation Awarded, not Appointed RO MoRTH Guwahati NH Division Silchar NH Division Silchar 6-Dec-19 28-Nov-19 MoRTH
50693 Construction of Silchar bypass on NH-53 in Assam Under Implementation Under Const. RO MoRTH Guwahati NH Division Silchar NH Division Silchar 6-Dec-19 28-Nov-19 MoRTH
52375 Re-Construction of a new bridge across river Tarapur at ch-270.15 km of NH-60 in the District of Bankura, West Bengal Job No-NH-60 / (WB)/ (15)/ 15-16-009-S&R (B) Under Implementation Under Const. RO MoRTH Kolkata NH Division-III NH Division-III 5-Dec-19 17-Oct-19 MoRTH
52376 Re-Construction of a new bridge across river Shali at ch- 247.00 km of NH-60 in the District of Bankura, West Bengal Under Implementation Under Const. RO MoRTH Kolkata NH Division-III NH Division-III 5-Dec-19 17-Oct-19 MoRTH
58474 Construction of ROB and its approaches in lieu of Unmanned Level Crossing at km 303.9 on NH-60 Under Implementation Awarded, not Appointed RO MoRTH Kolkata NH Division-III NH Division-III 5-Dec-19 17-Oct-19 MoRTH
58471 Construction of ROB and its approaches in lieu of level crossing No. KA-61 at km 194.850 of NH-60. Under Implementation Under Const. RO MoRTH Kolkata NH Division-III NH Division-III 5-Dec-19 17-Oct-19 MoRTH
58473 Construction of ROB and its approaches in lieu of Level Crossing No. 6/B/T at km 284.170 on NH-60 Under Implementation Under Const. RO MoRTH Kolkata NH Division-III NH Division-III 5-Dec-19 17-Oct-19 MoRTH
134727 "Reconstruction of minor bridges at chainage 181.868 km of NH-60 in the district Bankura ,West Bengal under EPC mode. Job No. 060-wb-2018-19/430" Under Implementation Under Const. RO MoRTH Kolkata NH Division-III NH Division-III 5-Dec-19 17-Oct-19 MoRTH
64832 Development of alignment of Fulahar Bridge approach on newly declared NH-131A from Chainage 49+05 Km to 51+20 Km and from 53+81 Km to 55+19 Km in the district Malda. Job No.- 131A-WB-2016-17/416 Under Implementation Under Const. RO MoRTH Kolkata NH Division-VII NH Division-VII 5-Dec-19 17-Oct-19 MoRTH
64849 Construction of 2 lane with paved shoulder from Km. 168.00 to 183.783 (Yesemyong to Unger) on Mokokchung to Tuli Section of NH-61 under EPC mode in the State of Nagaland. Under Implementation Under Const. RO MoRTH Guwahati EE Div-II EE Div-II 4-Dec-19 28-Nov-19 MoRTH
55596 Strengthening and widening to two lane with paved shoulder of NH-61 from Km. 40.00 to Km 72.40under EPC mode in the State of Nagaland during 2016-17(package-II from km 56.00 to km 72.40) Under Implementation Under Const. RO MoRTH Guwahati EE Div-I EE Div-I 4-Dec-19 28-Nov-19 MoRTH
53076 Strengthening and widening to two lane with paved shoulder of NH-61 from Km 40.00 to Km 72.40 under EPC mode in the State of Nagaland during FY 2016-17 (package-I from km 40.00 to km 56.00) Under Implementation Under Const. RO MoRTH Guwahati EE Div-I EE Div-I 4-Dec-19 28-Nov-19 MoRTH
122534 Improvement of City Portion of Dimapur and Kohima city of NH-39 (Package-I Dimapur City Km 106.90 to Km 124.20) Under Implementation Under Const. RO MoRTH Guwahati EE Div-I EE Div-I 4-Dec-19 28-Nov-19 MoRTH
123135 Strengthening profile correction and re-designing of pavement on NH-102B from km 25.50 to km 37.10 (saichal to Hliappui) and from km 46.10 to km 76.10 (pawlrang to Ngopa) in the State of Mizoram during 2017-18 Under Implementation Under Const. RO MoRTH Guwahati NH Division-3, Mizoram NH Division-3, Mizoram 28-Nov-19 28-Nov-19 MoRTH
55523 Construction for 2-laning with paved shoulder of NH-150 of stretch from Km 42/800 - Km 60/300 Under Implementation Under Const. RO MoRTH Guwahati NH Division-2, Mizoram NH Division-2, Mizoram 28-Nov-19 28-Nov-19 MoRTH
50647 Construction of a new 2-lane highway from km 38/00 to 71/00 in Mizoram to support Kaladan Multi Modal Transit Transport Project in Phase 'A' of SARDP-NE ( Package MM-II) Under Implementation Under Const. RO MoRTH Guwahati Multi-Model Project Division-II Multi-Model Project Division-II 28-Nov-19 28-Nov-19 MoRTH
124187 Strengthening from Km. 64/000 to Km. 69/000, 90/760 to 119/000 and Km. 126/000 to Km. 160/000 (Length=67.804 Km) of NH-36 for the year 2017-18 under Bakulia NH Division, Diphu in the state of Assam. (Job No. 036/AS/2017-18/176) Under Implementation Under Const. RO MoRTH Guwahati Bakulia NH Division Bakulia NH Division 28-Nov-19 28-Nov-19 MoRTH
55559 Strengthening with paved shoulder from km 30/0 to km 46/0, km 54/0 to km 61/0, km 69/0 to km 80/0 and km 80/0 to km 96/0 of NH-39 for the year 2015-16 including toll plaza (Job No.039-AS-2016-17-153) Under Implementation Under Const. RO MoRTH Guwahati Golaghat NH Division Golaghat NH Division 28-Nov-19 28-Nov-19 MoRTH
144359 Strengthening of pavement from km 61.00 to km 69.00 and widening of 1.5 m paved shoulder on either side and strengthening from km 103.00 to km 106.00 of NH-39 under Annual plan for the year 2018-19 under Golaghat NH Division, in the State of Assam on EPC mode (Job No. 039/AS/2018-19/186) Under Implementation Awarded, not Appointed RO MoRTH Guwahati Golaghat NH Division Golaghat NH Division 28-Nov-19 28-Nov-19 MoRTH
102109 Raising and strengthening including providing road side stone masonry longitudinal covered drain at Km. 107th of NH-39 under Golaghat NH Division, Golaghat under Annual Plan for the year 2017-18 in the state of Assam. (Job No. 039/AS/2017-18/174) Under Implementation Under Const. RO MoRTH Guwahati Golaghat NH Division Golaghat NH Division 28-Nov-19 28-Nov-19 MoRTH
55572 Strengthening of existing road from km. 653.364- 668,668.608 -690.329 of NH-37 (L=18.357 km), &construction of masonry drain under AP 2016-17 under NH Division, Dibrugarh in the State of Assam Under Implementation Under Const. RO MoRTH Guwahati NH Division Dibrugarh NH Division Dibrugarh 28-Nov-19 28-Nov-19 MoRTH
50690 Construction os 2-lane NH-37 with paved shoulders from end of ROB at Makum to NH-52 near Rupai (length=23.482km) under Dibrugarh NH Division SARDP-NE/NH-37/PWD/AS/2010-11/165 Under Implementation Under Const. RO MoRTH Guwahati NH Division Dibrugarh NH Division Dibrugarh 28-Nov-19 28-Nov-19 MoRTH
50646 Construction of a new - 2 Lane Highway from Km 0.00 (on NH-54 near Lawngtlai) to Km 38.00 (Crossing with GS Road) (Length=38 Km) in Mizoram to support Kaladan Multi Modal Transit Transport Project in Phase ‘A’ of SARDP-NE in the state of Mizoram Under Implementation Under Const. RO MoRTH Guwahati Multi-Model Project Division-I, Mizoram Multi-Model Project Division-I, Mizoram 28-Nov-19 28-Nov-19 MoRTH
50687 Construction of 2-lane Highway with paved shoulders between Dibrugarh - Panitola km 603/0 to 637/0 of NH-37 Under Implementation Under Const. RO MoRTH Guwahati NH Division Dibrugarh NH Division Dibrugarh 28-Nov-19 28-Nov-19 MoRTH
50686 2 laning from Kanubari to start of Bogibeel Bridge Under Implementation Under Const. RO MoRTH Guwahati NH Division Dibrugarh NH Division Dibrugarh 28-Nov-19 28-Nov-19 MoRTH
50699 Strengthening and widening of NH-44 from km. 206/500 to km. 222/00, km. 222/00 to km. 223/000, 247/000 to km. 252/280 and km. 263/191(Ex. Ch. 261/761 km.) to km. 272/241(Ex. Under Implementation Under Const. RO MoRTH Guwahati NH Division Karimganj NH Division Karimganj 28-Nov-19 28-Nov-19 MoRTH
50696 Katlicherra bypass from km. 47.00 - 52.00 Under Implementation Under Const. RO MoRTH Guwahati NH Division Karimganj NH Division Karimganj 28-Nov-19 28-Nov-19 MoRTH
50695 Dhaleshwari Bypass from km. 0.00 - 3.500 Under Implementation Under Const. RO MoRTH Guwahati NH Division Karimganj NH Division Karimganj 28-Nov-19 28-Nov-19 MoRTH
50700 Construction of 2-lane Patherkandi Bypass Job No.-044/AS/2014-15/122 Under Implementation Under Const. RO MoRTH Guwahati NH Division Karimganj NH Division Karimganj 28-Nov-19 28-Nov-19 MoRTH
148492 Special Repair to Bailey Bridge at Km 135/80 (R.Luaklui) & 136/50 (R.Luakzal) of NH-150 in the state of Mizoram. (Job No. TA/150/MZ/2015-16/84) Under Implementation Under Const. RO MoRTH Guwahati NH Division-2, Mizoram RO MoRTH Guwahati 28-Nov-19 28-Nov-19 MoRTH
145955 Repair and rehabilitation of existing pavement from km 110.00 to km 150.00 on NH-6 (Kawlkulh to Champai) in the State of Mizoram during 2018-19 on EPC mode. (Job No. 006/MZ/2018-19/117) Under Implementation Awarded, not Appointed RO MoRTH Guwahati NH Division-3, Mizoram RO MoRTH Guwahati 28-Nov-19 28-Nov-19 MoRTH
145951 Repair and rehabilitation of existing pavement from km 35.00 to km 80.00 on NH-6 (Keifand to Kawlkulh) in the State of Mizoram during 2018-19 on EPC mode. (Job No. 006/MZ/2018-19/116) Under Implementation Awarded, not Appointed RO MoRTH Guwahati NH Division-3, Mizoram RO MoRTH Guwahati 28-Nov-19 28-Nov-19 MoRTH
144357 Strengthening of existing 2-lane from km 445.00 to km 455.00 & km 475.00 to km 500.00 (Total Length = 35.00)of NH-52(New NH-15) under Annual plan for the year 2018-19 under Nagaon NH Division, Nagaon in the State of Assam on EPC mode (Job No. 052(New NH-15)/AS/2018-19/185) Under Implementation Awarded, not Appointed RO MoRTH Guwahati NH Division Nagaon RO MoRTH Guwahati 28-Nov-19 28-Nov-19 MoRTH
142854 Strengthening of existing pavement from km 15.35 to km 30.00 of NH-137A Imphal - Kakching Lamkhai section in the state of Manipur on EPC mode. (Job No. 137A/MN/2018-19/29) Under Implementation Awarded, not Appointed RO MoRTH Guwahati NH-Division No I Manipur RO MoRTH Guwahati 28-Nov-19 28-Nov-19 MoRTH
124230 Widening of Bridges No.3/1, 6/1, 8/1, 12/1, 17/1, 19/1, & 29/1 on NH-52 under Annual Plan under Rangia NH Division in the State of Assam. (Job No. 015/AS/2017-18/181) Under Implementation Under Const. RO MoRTH Guwahati NH Division Rangia RO MoRTH Guwahati 28-Nov-19 28-Nov-19 MoRTH
123131 Rehabilitation of distress bridges at Ch. 91.60 Km, Ch. 94.60 Km, Ch. 97.40 Km, Ch. 117.90 Km, 124.60 Km, Ch. 138.80 Km, Ch. 169.70 Km, Ch. 171.10 Km, Ch. 178.00 Km, Ch. 180.20 Km, Ch. 180.40 Km, Ch. 182.60 Km, Ch. 188.50 Km, on NH-62 in the state of Meghalaya.Job No. 062/MG/2016-17/150 Under Implementation Under Const. RO MoRTH Guwahati NH Division Baghmara RO MoRTH Guwahati 28-Nov-19 28-Nov-19 MoRTH
80707 Installation of crash barriers on various streches of national Highways in the state of Mizoram. Job No. NHs-MZ-2016-17-RSCE-031 Under Implementation Under Const. RO MoRTH Guwahati NH Division-1, Mizoram RO MoRTH Guwahati 28-Nov-19 28-Nov-19 MoRTH
67902 Improvement of City portion of Kohima and Dimapur City of Nh-39 in the State of Nagaland under EPC mode during 2016-17 (Package-II Kohima City from Km 177.60 to Km 187.60) Under Implementation Under Const. RO MoRTH Guwahati EE Div-I RO MoRTH Guwahati 28-Nov-19 28-Nov-19 MoRTH
67328 Reconstruction of 6 nos. of weak SPT Bridges with bailey Bridges including approaches (Br. No 181/2, 174/4,201/7 etc) on NH-62 (Job No: 062/MG/2016-17/142) Length (Km - 195.40) Under Implementation Under Const. RO MoRTH Guwahati NH Division Baghmara RO MoRTH Guwahati 28-Nov-19 28-Nov-19 MoRTH
67323 Reconsttrucion of Weak Culverts Nos. 139/4, 142/2, 158/2,158/6 etc. on NH-62 including Retaining Wall, unlined drains in Meghalaya (Job No: 062/MG/2016-17/141) Length (Km - 195.40) Under Implementation Under Const. RO MoRTH Guwahati NH Division Baghmara RO MoRTH Guwahati 28-Nov-19 28-Nov-19 MoRTH
55565 Strengthening with paved shoulders in Km 13 to 15, Km 20 to 23, Km 35 and Km 36th and Km 57 to 63rd (Total length=16.870 Km) ubnder Rangia NH Under Implementation Under Const. RO MoRTH Guwahati NH Division Rangia RO MoRTH Guwahati 28-Nov-19 28-Nov-19 MoRTH
55506 Strengthening of existing two lane pavements i/c paved shoulder on NH No. 150 from Km 433.00 to Km 454.798 Under Implementation Under Const. RO MoRTH Guwahati NH-Division No III Manipur RO MoRTH Guwahati 28-Nov-19 28-Nov-19 MoRTH
55505 Strengthening of existing two lane pavements i/c paved shoulder on NH No. 150 from Km 412.00 to Km 433.00 Under Implementation Under Const. RO MoRTH Guwahati NH-Division No III Manipur RO MoRTH Guwahati 28-Nov-19 28-Nov-19 MoRTH
55500 Widening 4-lane to 6-lane from Km 454.798 to Km 459.600 and Widening of formation from Km 474.00 to Km 488.00 and construction of Paved shoulder from Km 467.00 to Km 474.00 Under Implementation Under Const. RO MoRTH Guwahati NH-Division No III Manipur RO MoRTH Guwahati 28-Nov-19 28-Nov-19 MoRTH
53061 Paikan-Dalu Under Implementation Under Const. RO MoRTH Guwahati NH Cum Tura Central Division RO MoRTH Guwahati 28-Nov-19 28-Nov-19 MoRTH
53046 Construction of 1.50 m wide paved shoulder on eighter side of 10 km stretch from km 308.00 to km 318.00 along with widening of intermediate lane to 2-lane from km 313.00 to km 318.00 on Churaibari - Agartala Section of NH -8 (old NH -44) in Tripura. Under Implementation Under Const. RO MoRTH Guwahati NH-Division Kumarghat RO MoRTH Guwahati 28-Nov-19 28-Nov-19 MoRTH
53029 Construction of longitudinal drains at stretches from 134/00 to km 146/300 Under Implementation Under Const. RO MoRTH Guwahati NH Division Guwahati RO MoRTH Guwahati 28-Nov-19 28-Nov-19 MoRTH
50711 2 Laning of Lumding-Diphu-Manja Road, Haflong-Jatinga Road, Baska-Barama Road, Morigaon-Jagiroad Road, Kokrajhar-Karigaon Road and Udalguri-Routa Road in the state of Assam (Length = 146km) under SARDP-NE, Phase A in the state of Assam (Job No. SARDP Under Implementation Under Const. RO MoRTH Guwahati NH Division Nagaon RO MoRTH Guwahati 28-Nov-19 28-Nov-19 MoRTH
50707 Construction of Proposed North Lakhimpur By-pass from existing km 338/924 to km 349/213 of NH-52 in the state of Assam (Job No.052-AS-2011-12-099) Under Implementation Under Const. RO MoRTH Guwahati NH Division Nagaon RO MoRTH Guwahati 28-Nov-19 28-Nov-19 MoRTH
50698 2 laning of Goalpara- Solmari road/189 Under Implementation Under Const. RO MoRTH Guwahati NH Division Guwahati RO MoRTH Guwahati 28-Nov-19 28-Nov-19 MoRTH
50649 Widening to 2-Lane, re-alignment and geometric improvement from Km 11/00 to Km 114/618 of NH 44 A Under Implementation Under Const. RO MoRTH Guwahati NH Division-1, Mizoram RO MoRTH Guwahati 28-Nov-19 28-Nov-19 MoRTH
50648 Construction of a new 2-lane highways from km 71/00 to km 99/83 in Mizoram to support Kaladan Multi Modal Transit Transport Project in SARDP NE PhaseA Under Implementation Under Const. RO MoRTH Guwahati Multi-Model Project Division-II RO MoRTH Guwahati 28-Nov-19 28-Nov-19 MoRTH
61096 Strengthening of road stretches along with provision for Retaining walls, Breast walls & hillside drains from 0.00 km to 4.40 km & from 14.0 km to 28.0 km of NH-10 in SBD mode (Job 408) Under Implementation Under Const. RO MoRTH Kolkata NH Division-IX NH Division-IX 11-Nov-19 17-Oct-19 MoRTH
52356 Rehabilitation of landslide location with slope protection and drainage improvement at Tindharia on NH 55 (km 50 + 155 to 50 + 182, km 52+ 650 to Km 52+ 800 and Km 53 +452 to km 53+ 475) Under Implementation Under Const. RO MoRTH Kolkata NH Division-IX NH Division-IX 11-Nov-19 17-Oct-19 MoRTH
52319 Rehabilitation of landslide location along with slope protection and drainage improvement at Paglajhora on NH-55 (km 43+500 to 43+950) Under Implementation Under Const. RO MoRTH Kolkata NH Division-IX NH Division-IX 11-Nov-19 17-Oct-19 MoRTH
58475 Construction of twins 2-lane ROB and its approaches in replacement of Level Crossing at km 615.5 of NH-31 Under Implementation Under Const. RO MoRTH Kolkata NH Division-IX NH Division-IX 11-Nov-19 17-Oct-19 MoRTH
58476 Construction of twins 2-lane ROB and its approached in liue of Level Crossing at km 652.6 of NH-31 Under Implementation Under Const. RO MoRTH Kolkata NH Division-IX NH Division-IX 11-Nov-19 17-Oct-19 MoRTH
58477 Construction of ROB and its approaches in lieu of Level Crossing at km 661.100 on NH-31 Under Implementation Under Const. RO MoRTH Kolkata NH Division-IX NH Division-IX 11-Nov-19 17-Oct-19 MoRTH
64837 Upgradation of NH-31C with a minimum of 2-lane with paved shoulder configuration starting from km 105.000 to km 145.632 (total length 40.632 km) in Jalpaiguri on EPC mode Job-417) Under Implementation Under Const. RO MoRTH Kolkata NH Division-IX NH Division-X 11-Nov-19 17-Oct-19 MoRTH
52352 Rehabilitation & upgradation of Pundibari to Baxirhat from Km 770 to Km 814. Under Implementation PCOD RO MoRTH Kolkata NH Division-X NH Division-X 11-Nov-19 17-Oct-19 MoRTH
123147 Strengthening of NH - 60 from Ch. 401.00 Km. (Nalhati) to 422.450 Km. (Moregram) along with Improvement of Shoulder in the districts of Birbhum and Murshidabad in the State of West Bengal under AP-2017-18 (Job No. 060-WB-2017-18/427). Under Implementation Under Const. RO MoRTH Kolkata NH Division-XII NH Division-XII 11-Nov-19 17-Oct-19 MoRTH
143021 Improvement of NH-60 from km 330.00 to km 355.00 & from km 360.00 to km 374.00 except the stretch from km 337.703 to km 339.046 (for Suri ROB) by way of Strengthening of existing carriageway and laying of wearing course from km 355.00 to km 360.00 in the district of Birbhum, West Bengal under EPC mode . Job No.060-WB-2018-19/433 Under Implementation Under Const. RO MoRTH Kolkata NH Division-XII NH Division-XII 11-Nov-19 17-Oct-19 MoRTH
58484 Construction of ROB and its approaches in lieu of LC No. 10/B/T at Km 307.050 of NH-60. Under Implementation Awarded, not Appointed RO MoRTH Kolkata NH Division-XII NH Division-XII 11-Nov-19 17-Oct-19 MoRTH
58485 Construction of ROB and its appraoches in lieu of LC no.21/SPL/E at Km 338.000 on NH-60 Under Implementation Awarded, not Appointed RO MoRTH Kolkata NH Division-XII NH Division-XII 11-Nov-19 17-Oct-19 MoRTH
52351 Construction of PSC Girder bridge over river Sal & Hinglow in place of damaged vented causeway at Km 314.330 & Km 309.800 of NH-60 Under Implementation Under Const. RO MoRTH Kolkata NH Division-XII NH Division-XII 11-Nov-19 17-Oct-19 MoRTH
134725 "Rehabilitation of 9 (Nine) damaged Bridges/ROB along NH-60 during the year of 2018-19 Iin the district of Birbhum. Job No.060-WB-2018-19/429" Under Implementation Under Const. RO MoRTH Kolkata NH Division-XII NH Division-XII 11-Nov-19 17-Oct-19 MoRTH
148525 Construction of Fly Over (Bridges) at 03 major 4- arm junciton at three places Ring road junctions A B & G Ch. 10/3, 13/3 & 14/6 by passing in the alignment of newly of newly declared NH 848 A in UT of DNH on EPC mode. Under Implementation Under Const. RO MoRTH Gandhinagar NH Division Silvasa RO MoRTH Gandhinagar 25-Oct-19 25-Oct-19 MoRTH
148524 Upgradation Strengthening for the road stretch from Dadra to Tighra (Ch. 4/800 to 7/339 Km) and Samaravrni to Rakholi Bridge (Ch. 14/500 to 19/500 Km.) of NH 848 A at Silvassa, Dadra & Nagar Haveli UT (on EPC mode) Under Implementation Under Const. RO MoRTH Gandhinagar NH Division Silvasa RO MoRTH Gandhinagar 25-Oct-19 25-Oct-19 MoRTH
147690 Strengthening to A'bad-Dandi between Km 63/770 to 71/200 section (Dabhan-Nadiad city-DDIT Road) on NH-64 in the state of Gujarat on EPC basis. Under Implementation Under Const. RO MoRTH Gandhinagar NH Division Varodara RO MoRTH Gandhinagar 25-Oct-19 25-Oct-19 MoRTH
58455 Widening up to P.S.S. & Strengthening to Km. 0/0 to 11/0 (Una - Delvada) Under Implementation PCOD RO MoRTH Gandhinagar NH Division Rajkot RO MoRTH Gandhinagar 25-Oct-19 25-Oct-19 MoRTH
144112 "Improvement of Riding Quality (IRQ) from km 654.00 to km 670.00 of NH-31 in the district of Jalpaiguri, West Bengal during the year 2018-19 on EPC mode. (Job No.- 031-WB-2018-19/437)" Under Implementation Under Const. RO MoRTH Kolkata NH Division-IX RO MoRTH Kolkata 17-Oct-19 17-Oct-19 MoRTH
148716 Road Safety works with Crash barrier, Parapet, Delinaters & road Protection work Hill Side & Valley Side etc from Km 5.00 to 77.10 on NH-309B in the State of Uttarakhand under Annual Plan 2018-19 Under Implementation Awarded, not Appointed RO MoRTH Dehradun NH Division Ranikhet RO MoRTH Dehradun 12-Oct-19 12-Oct-19 MoRTH
148714 Construction of 24 M Span RCC girder Bridge in km 7.00(H.M. 6-8) NH-309A in the State of Uttarakhand under Annual Plan 2018-19 Under Implementation Awarded, not Appointed RO MoRTH Dehradun NH Division Lohaghat RO MoRTH Dehradun 12-Oct-19 12-Oct-19 MoRTH
148713 Construction of drain & laying of interlocking tiles in Km. 18, 21, 27 & 28 in populated area. Under Implementation Under Const. RO MoRTH Dehradun NH Division Haldwani RO MoRTH Dehradun 12-Oct-19 12-Oct-19 MoRTH
148712 Protection work in km 4.00 to 63.00 on NH-121(309) in NH-87 (New NH-109) under NH(O) 2018-19 in the State of Uttarakhand under Annual Plan 2018-19 Under Implementation Under Const. RO MoRTH Dehradun NH Division Haldwani RO MoRTH Dehradun 12-Oct-19 12-Oct-19 MoRTH
148710 Restoration and protection work in km 89.100 to 123.000 in NH-87 (New NH-109) under NH(O) 2018-19 in the State of Uttarakhand under Annual Plan 2018-19 Under Implementation Under Const. RO MoRTH Dehradun NH Division Haldwani RO MoRTH Dehradun 12-Oct-19 12-Oct-19 MoRTH
148708 Protection work in km 92.100 to 123.000 in NH-87 (New NH-109) under NH(O) 2018-19 in the State of Uttarakhand under Annual Plan 2018-19 Under Implementation Under Const. RO MoRTH Dehradun NH Division Haldwani RO MoRTH Dehradun 12-Oct-19 12-Oct-19 MoRTH
148707 Protection work in km. 150.00 To 165.00 on NH-119(new No. 534) Under Implementation Awarded, not Appointed RO MoRTH Dehradun NH Division Dhumakot RO MoRTH Dehradun 12-Oct-19 12-Oct-19 MoRTH
148706 Strengthening work from Km 70.00 to Km 78.00 on NH-121 in state of Uttarakhand Under Implementation Awarded, not Appointed RO MoRTH Dehradun NH Division Dhumakot RO MoRTH Dehradun 12-Oct-19 12-Oct-19 MoRTH
148704 Construction of 4 Nos bridges viz 24 m span bridge at km. 121 & km. 138, 42 m span bridge at km. 141 and 10 m span bridge at km. 149 on NH-121 (New No. 309) in the State of Uttarakhand Under Implementation Awarded, not Appointed RO MoRTH Dehradun NH Division Dhumakot RO MoRTH Dehradun 12-Oct-19 12-Oct-19 MoRTH
148703 Construction of 5 Nos bridges viz 30 m span bridge at km. 152, 12 m span bridge at km. 156, 42 m span bridge at km. 158, 30 m span bridge at km. 163 and 24 m span bridge at km. 165 on NH-121 (New No. 309) in the State of Uttarakhand Under Implementation Awarded, not Appointed RO MoRTH Dehradun NH Division Dhumakot RO MoRTH Dehradun 12-Oct-19 12-Oct-19 MoRTH
148702 Strengthening work from km. 101.00 to 107.00 on NH-123(New No. 507) in the State of Uttarakhand Under Implementation Awarded, not Appointed RO MoRTH Dehradun NH Division Barkot RO MoRTH Dehradun 12-Oct-19 12-Oct-19 MoRTH
124317 Construction of 2 lane with paved shoulder of Kund Bypass from Design Km 35.130 to Km 47.700 (existing Km 33.130 to Km 41.260) of NH-109 in the State of Uttarakhand Under Implementation Under Const. RO MoRTH Dehradun NH Division Rudraprayag RO MoRTH Dehradun 12-Oct-19 12-Oct-19 MoRTH
80689 Rehabilitation and up gradation to 2-lane with paved shoulder from existing km 172.900 to km 194.150 (Design chainage km 49.300 to km 70.300) on dharasu to yamunotri road of NH-134(old NH 94) in the state of uttarakhand under improvement of NH connectivity to chardham. Under Implementation Under Const. RO MoRTH Dehradun NH Division Barkot RO MoRTH Dehradun 12-Oct-19 12-Oct-19 MoRTH
80665 Construction of 4 nos bridges in km. 139 to 196 on NH-119 Under Implementation Under Const. RO MoRTH Dehradun NH Division Dhumakot RO MoRTH Dehradun 12-Oct-19 12-Oct-19 MoRTH
80597 Widening and Strengthening/ Reconstruction of Existing 2-Lane To 2 Lane with Paved Shoulder Configuration from existing km 338+100 (Design km 333.400) to km 368+000 (Design km 360.579) excluding existing km 349+800 to km. 355+495 (Kaliyasaur Bypass) of NH-58 In the State of Uttarakhand through an Engineering, Procurement and Construction (EPC) Contract Under Implementation Under Const. RO MoRTH Dehradun NH Division Srinagar RO MoRTH Dehradun 12-Oct-19 12-Oct-19 MoRTH
80592 Construction of 15 M span RCC motor bridge ate km. 143.090 on NH-707A Under Implementation Under Const. RO MoRTH Dehradun NH Division Doiwala RO MoRTH Dehradun 12-Oct-19 12-Oct-19 MoRTH
80591 Constrcution of 18 M span RCC motor bridge at km. 48.350 on NH-707A Under Implementation Under Const. RO MoRTH Dehradun NH Division Doiwala RO MoRTH Dehradun 12-Oct-19 12-Oct-19 MoRTH
80590 Strengthening from km. 52.350 to km. 61.750, km. 70.750 to 72.825 and km. 80.00 to 83.00 on NH-707A in the state of uttarakhand. Under Implementation Under Const. RO MoRTH Dehradun NH Division Doiwala RO MoRTH Dehradun 12-Oct-19 12-Oct-19 MoRTH
80585 Installation of crash barriers on various stretches of National Highways in the state of Uttarakhand Under Implementation Under Const. RO MoRTH Dehradun NH Division Doiwala RO MoRTH Dehradun 12-Oct-19 12-Oct-19 MoRTH
66982 Rehabilitation and upgradation to 2 lane with paved shoulder configuration from km 122.00 (Dharasu Bend) to km 147.230 (Silkyara Bend) of NH-94 in the state of Uttarakhand Under Implementation Under Const. RO MoRTH Dehradun NH Division Barkot RO MoRTH Dehradun 12-Oct-19 12-Oct-19 MoRTH
64900 Construction of 12.00 M span RCC motor bridge at km. 5.25 of NH-707A in the State of Uttarakhand Under Implementation Under Const. RO MoRTH Dehradun NH Division Doiwala RO MoRTH Dehradun 12-Oct-19 12-Oct-19 MoRTH
64897 Construction of 30.00 M span RCC motor bridge at km. 43.650 of NH-707A in the State of Uttarakhand Under Implementation Under Const. RO MoRTH Dehradun NH Division Doiwala RO MoRTH Dehradun 12-Oct-19 12-Oct-19 MoRTH
64893 Improvement /Widening to 2-lane with paved shoulder including major bridge & protection work of Paligaad market on Hill side and valley side from km. 196.00 to 197.00 on NH-94 (New No. 134) in UK Under Implementation Under Const. RO MoRTH Dehradun NH Division Barkot RO MoRTH Dehradun 12-Oct-19 12-Oct-19 MoRTH
62568 RECONSTRUCTION WITH GEOMETRIC IMPROVMENT OF EXISTING INTERMEDIATE LANE TO 2 LANE WITH PAVED SHOULDER CONFIGEURATION FROM KM. 28.600 TO 59.420 (DSIGN CHAINAGE 28.320 TO KM 58.603) of NH-94 IN THE STATE OF UTTARAKHAND ON EPC MODE UNDER IMPROVEMENT TO N Under Implementation Under Const. RO MoRTH Dehradun PIU-Dehradun, MoRTH RO MoRTH Dehradun 12-Oct-19 12-Oct-19 MoRTH
62564 Construction of 2-Lane ROB and its approaches in lieu of existing level Crossing (L.C.No. 39-B) at Km 158.525 on NH-74 in the state of Uttarakhand on EPC Mode Under Implementation Under Const. RO MoRTH Dehradun NH Division Haldwani RO MoRTH Dehradun 12-Oct-19 12-Oct-19 MoRTH
60146 Widening of existing single lane road to two lane with paved shoulder from km. 235.00 to 268.00 of NH-58 including 600 m marine drive viaduct portion near Byasi in Uttarakhand under EPC mode Under Implementation PCOD RO MoRTH Dehradun NH Division Srinagar RO MoRTH Dehradun 12-Oct-19 12-Oct-19 MoRTH
60145 Reconstruction with geometric improvement of existing 2L/IL to 2L with paved shoulder from km. 268.00 to 300.00 of NH-58 in Uttarakhand under EPC mode Under Implementation PCOD RO MoRTH Dehradun NH Division Srinagar RO MoRTH Dehradun 12-Oct-19 12-Oct-19 MoRTH
54164 Reconstruction with geometric improvement of existing intermediate lane to 2 lane with paved shoulder configuration from km 1.95 to km 28.600 (excluding the stretch from km 13.800 to km 18.550) of NH-94 in the state of Uttarakhand on EPC mode. Under Implementation Under Const. RO MoRTH Dehradun PIU-Dehradun, MoRTH RO MoRTH Dehradun 12-Oct-19 12-Oct-19 MoRTH
54162 Reconstruction with geometric improvement of existing 2 lane/intermediate lane to 2lane with paved shoulder configuration from km. 300 to 338 of NH-58 in the State of Uttarakhand under EPC mode Under Implementation Under Const. RO MoRTH Dehradun NH Division Srinagar RO MoRTH Dehradun 12-Oct-19 12-Oct-19 MoRTH
50289 Protection work of NH-119 (New No. 534) at KM- 149 HM (8-10) and KM- 150 HM (8-10) in the State of U Under Implementation Under Const. RO MoRTH Dehradun NH Division Dhumakot RO MoRTH Dehradun 12-Oct-19 12-Oct-19 MoRTH
50276 Widening and Strenthening of existing intermediate / 2-lane to 2-lane with paved shoulder configuration from km. 0.00 (Design km. 0.00) to km. 16.440 (Design km. 18.700) including existing 3.470 km of Rudraprayag Bypass of NH-109 in the State of UK Under Implementation Under Const. RO MoRTH Dehradun NH Division Rudraprayag RO MoRTH Dehradun 12-Oct-19 12-Oct-19 MoRTH
50268 Widening of existing 2 lane to 4 lane in km. 156.00 to 161.00 (I.S.B.T. to Ajabpur Railway Crossing) of NH-72 (New No-07) in UK Under Implementation Under Const. RO MoRTH Dehradun NH Division Doiwala RO MoRTH Dehradun 12-Oct-19 12-Oct-19 MoRTH
50262 Mitigation of Lambagarh Landslide at km. 504.309 onNH-58 in the State of Uttarakhand Under Implementation Under Const. RO MoRTH Dehradun NH Division Rudraprayag RO MoRTH Dehradun 12-Oct-19 12-Oct-19 MoRTH
139919 Washim(km 92.200) to Pangare(134.500) of NH-161 in Maharashtra Under Implementation Under Const. RO-Nagpur PIU-Washim PD-Washim 5-Feb-20 10-Dec-19 NHAI
139832 Hiran River to Sindoor River (Km.66.00 - Km.130.00) Under Implementation Under Const. RO-Bhopal PIU-Narsinghpur PD-Narsinghpur 4-Feb-20 9-Oct-19 NHAI
139348 Yedshi (Km.100.000) to Aurangabad (Km.290.200) Under Implementation PCOD RO-Nagpur PIU-Aurangabad PD-Aurangabad 4-Feb-20 10-Dec-19 NHAI
140365 Delhi/ Haryana Border to Rohtak section including Bahadurgarh and Rohtak by-passes Under Implementation PCOD RO-Chandigarh PIU-Rohtak PD-Rohtak 3-Feb-20 6-Aug-19 NHAI
139333 Tirupati - Tiruttani - Chennai Section of NH-205 in the State of Andhra Pradesh and Tamil Nadu Under Implementation PCOD RO-Chennai PIU-Chennai PD-Chennai 7-Jan-20 11-Jan-20 NHAI
139461 Chennai-Tada Under Implementation Under Const. RO-Chennai PIU-Chennai PD-Chennai 7-Jan-20 11-Jan-20 NHAI
139870 (i) Balance work of TPP Road - (ii) Improvement of MORR and IRR; (iii) Improvement of Ennore Express Under Implementation PCOD RO-Chennai PIU-Chennai PD-Chennai 7-Jan-20 11-Jan-20 NHAI
139388 Solan - Kaithlighat Section of NH-22 Now NH-5 from Km. 106.139 to Km.129.05 Under Implementation Under Const. RO-Shimla PIU-Shimla PD-Shimla 6-Jan-20 7-Nov-19 NHAI
139839 Shimla Bypass (Kaithlighat (Km 129.050) to Dhalli (Km 156.507) Under Implementation Under Const. RO-Shimla PIU-Shimla PD-Shimla 6-Jan-20 7-Nov-19 NHAI
139843 Parwanoo (Km 67.00) to Solan (Km 106.14) of NH-22 in Himachal Pradesh Under Implementation Under Const. RO-Shimla PIU-Shimla PD-Shimla 6-Jan-20 7-Nov-19 NHAI
139780 Maheshkunt -Saharsa-Purnea Pkg II Under Implementation Under Const. RO-Patna PIU-Begusarai PD-Begusarai 4-Jan-20 16-Apr-19 NHAI
139893 Myanmar Project (Yargi - Kalewa) Under Implementation Under Const. RO-Guwahati PIU-Myanmar PD-Myanmar 8-Oct-18 26-Dec-19 NHAI

MoRTH LA Notifications

1033

NHAI LA Notifications

2828

NHIDCL LA Notifications

172

Total LA Notifications

4033

*  "From April 2014 to March 2018. Based on online data from PMIS as well as offline inputs from Monitoring Division collated for all agencies (Road Wing,NHAI,NHIDCL)."

#  "3 States (Andhra Pradesh, Telangana & Madhya Pradesh) are not integrated with Sarathi Portal."